Wednesday, March 1: The duration of this work has been extended to March 31, 2017.

February 20, 2017: Schedule of activity now to include weekday work, beginning Wednesday, February 15.

January 20, 2017: The duration of this activity has been extended to February 25.

Summary

Regional Connector Constructors (RCC) will begin piling activities at the 5th St. and Flower St. intersection.

Work is anticipated to begin Wednesday, February 15, 2017 and continue for approximately four weeks.

Anticipated work hours, weather permitting:

  • Monday through Friday: 9 am to 3:30 pm
  • Saturdays: 7 am to 9 pm
  • Sundays, as needed: 7 am to 9 pm

At least one lane will be maintained at all times on southbound Flower St. on January 21. Starting on January 27, Flower St. will resume full closure from 4th St. to 5th St. and local access will be maintained.

Essentials

Pedestrian access will be maintained. Access to driveways will be maintained at all times.

What to Expect

Lane reductions will be in place on Flower St. between 5th St. and 6th St., along with lane reductions on westbound 5th St. between Olive St. and Flower St.

Left turns from westbound 5th St. to southbound Flower St. will be maintained during work hours.

Starting on January 27, right turns from westbound 5th St. to northbound Flower St. will be maintained during piling allowing local access.

Program Notes

Eat, Shop, Play Local

Website | Upcoming Events | Twitter | Facebook

Was this information useful?

Share this page on
Advertisement
Close Search Window

Search metro.net, The Source, and El Pasajero