Summary
Regional Connect Constructors (RCC) will install geotechnical instruments along 2nd St. between San Pedro St. and Los Angeles St.
Work is anticipated to begin on Wednesday, November 2, and continue for three weeks. Anticipated work hours are from 9 a.m. to 3:30 p.m., Monday through Friday.
Thru traffic will be maintained at all times.
Essentials
Local access for driveways will be maintained during installation.
What to Expect
Work will begin on the south side of 2nd St. and then switch to the north side of 2nd St.
November 2–10: Eastbound 2nd St.
A lane shift will occur on eastbound 2nd St. between San Pedro St. and Los Angeles St.
Metered parking may be restricted during the work hours.
November 14–18: Westbound 2nd St.
A parking lane restriction will occur on westbound 2nd St. between San Pedro St. and Los Angeles St. during work hours.
Thru traffic will be maintained during work hours. All crosswalks and pedestrian access will be available.