Traffic reconfiguration for deck installation on Flower St from 3rd St to 5th St

Summary

In preparation of cut and cover activities, traffic on Flower St from 4th St to 5th St will be reconfigured on Saturday, October 1, 2016 from 8am to 6pm.

Regional Connector Constructors (RCC) will restripe Flower St from 3rd St to 5th St while maintaining one thru traffic lane.

Activities include grinding, restriping traffic lanes and traffic signal modifications.

At the completion of this activity, Flower St will be reduced to three southbound lanes and one right turn pocket to westbound 5th St. This configuration will remain in place for approximately 44 months.

Pile installation on the eastside of Flower St will take place on Saturdays from 8am to 6pm and on Sundays, from 10am – 6pm Monday – Friday activities include cap beam installation from 7am to 9pm behind k-rail.

Essentials

Local and thru access will be maintained on Saturday, October 1.

Pedestrian access will be maintained outside the construction area.

Flaggers will be onsite to facilitate access.

What to Expect

A work zone will be in place on the eastside of Flower St from 4th St to 5th St. The work zone will be in place for 44 months to facilitate construction of the tunnel box.

Installation of temporary road way – decking - is anticipated to start October 14, 2016.

Deck installation requires full street closures of Flower St from 3rd St to 5th St starting 6pm on Friday through 5am Monday.

Weekend closures of Flower St from 3rd St to 5th St will take place for approximately 14 weekends, excluding Holidays.

Program Notes

Eat, Shop, Play Local

Website | Upcoming Events | Twitter | Facebook

Was this information useful?

Share this page on
Advertisement
Close Search Window

Search metro.net, The Source, and El Pasajero