Piling and Decking Installation behind k rail at 2nd/Broadway Station

Summary

In preparation for the future 2nd/Broadway Station, Regional Connector Constructors (RCC) will be continuing with utility relocation, piling and starting decking installation.

The activities behind k-rail will continue for next four months and anticipated work hours are 7 a.m. to 3:30 p.m. and 3:30 p.m. to midnight Monday through Friday. Saturdays will be from 8 a.m. to 6 p.m.

Work will occur behind current k-rail within current traffic closures.

Essentials

Piing installation includes pre-trenching, pile drilling, pile installation, concrete/backfill operations and cap beam installation.

Decking installation will include excavation, placing steel plates, welding, placement of precast concrete deck panels and asphalt paving/compaction for decking installation.

What to Expect

Pedestrian access is available outside of work zone. Sound barriers and blankets will be in place.

Program Notes

Eat, Shop, Play Local

Website | Upcoming Events | Twitter | Facebook

Was this information useful?

Share this page on
Advertisement
Close Search Window

Search metro.net, The Source, and El Pasajero