Construction Activities 1st/Alameda Behind K-rails

Summary

Regional Connector Constructors (RCC) will continue construction behind k-rail on 1st St. between Alameda and Hewitt St. installing piles.

Work will resume on Monday, November 14, 2016 and continue through December 2016.

Anticipated work hours are from 7 a.m. to 9 p.m., Monday through Friday and 8 a.m. to 6 p.m. on Saturdays. The activities include potholing and pile installation.

Essentials

Pedestrian access will be maintained at all times.

What to Expect

Work will continue within the current work zone, No additional traffic closures are needed. Sound barriers and blankets will be in place as needed basis.

Program Notes