Geotechnical Instrumentation Installation on the east side of Flower St, between 3rd and 4th St

Update

Monday, November 14: The duration of this activity has been extended an additional two weeks (through November 27).

Friday, November 4: The duration of this activity has been extended an additional week (through November 13).

Friday, October 28: The duration of this activity has been extended an additional week (through November 6).

Summary

Regional Connect Constructors (RCC) will continue installing geotechnical instrumentation on Flower St. between 3rd St. and 4th St.

Work continues on November 14 for an additional two weeks. Anticipated work hours from 9 a.m. to 3:30 p.m., Monday through Friday.

A northbound directional closure of Flower St. between 3rd and 4th St will take place during installation.

Essentials

Geotechnical instrumentation is needed to monitor the underground work during construction.

What to Expect

A southbound lane reduction between 3rd and 4th St will take place due to work zone.

Local access to Bank of America Plaza and J2 Garage will be maintained from southbound Flower St. between 3rd St. to 4th St. Flagger will be available onsite to assist with local access.

Pedestrian access will be maintained during work hours.

Northbound Flower St. between 3rd to 4th St Detour:
Exiting Bank of America Plaza and J2 Garage, left on Flower St., right on 5th St., right on Figueroa St., and back on northbound Figueroa St.