Full Street Closure of Slauson Av at Crenshaw Bl

Summary

As part of Metro’s Crenshaw/LAX Transit Project, Walsh-Shea Corridor Constructors (WSCC) will be working on the restoration of the roadway, which will include demolition, excavation, backfill, and paving of Slauson Av and Crenshaw Bl. This continuous closure of Slauson Av at Crenshaw Bl will be conducted in two phases starting at 6 am on Friday, October 16, 2020.

Essentials

WHAT: Full street closure
WHEN: Starting 6 am Friday, October 16, 2020, through 3 pm Monday, October 26, 2020. Weather permitting.
WHERE: Slauson Av at Crenshaw Bl
DURATION: Six days

What to Expect

Phase 1: Starting 6 am Friday, October 16, 2020, through 3 pm Monday, October 19, 2020.

  • A closure of Slauson Av between Victoria Av and Crenshaw Bl.
  • A closure of Slauson Av between 11th Av and Crenshaw Bl.

Phase 1: Slauson Av Eastbound Detour:

South on Crenshaw Bl
East on Florence Av
North on Western Av
East on Slauson Av

Phase 1: Slauson Av Westbound Detour:

South on Western Av
West on Florence Av
North on West Bl
West on Slauson Av

Phase 2: Starting 6 am Friday, October 23, 2020, through 3 pm Monday, October 26, 2020.

  • An intersection closure of eastbound/westbound Slauson Av at Crenshaw Bl.
  • Right turns from Slauson Av on to Crenshaw Bl will remain open.

- Lane closures adjacent to the construction activity on Crenshaw Bl.
- Driveway access may be restricted.
- Access to emergency responders will be maintained.