Summary
As part of Metro’s Crenshaw/LAX Transit Project, Walsh-Shea Corridor Constructors (WSCC) will be working on the restoration of the roadway which will include demolition, excavation, backfill, and paving of Locust St. This work will require the full closure of Locust St south of Florence Av for three consecutive days starting at 6 am on Friday, October 16, 2020.
Essentials
WHAT: Full street closure
WHEN: Starting 6 am Friday, October 16, 2020, through 6 pm Sunday, October 18, 2020. Weather permitting.
WHERE: Locust St and Florence Av
DURATION: Three days
What to Expect
- Lane closures adjacent to the construction activity on Florence Av.
- Access to emergency responders will be maintained.