Full Street Closure of Crenshaw Bl at 48th St

Summary

As part of Metro’s Crenshaw/LAX Transit Project, Walsh-Shea Corridor Constructors (WSCC) will be working on the restoration of the roadway, which will include demolition, excavation, backfill, and paving of Crenshaw Bl and 48th St. This continuous closure of Crenshaw Bl and 48th St will be conducted in two phases starting at 6 am on Monday, September 28, 2020.

Essentials

WHAT: Full street closure
WHEN: Starting 6 am Monday, September 28, 2020, through 6 pm Friday, October 9, 2020. Weather permitting.
WHERE: Crenshaw Bl and 48th St
DURATION: Ten days

What to Expect

Phase 1: Starting 6 am Monday, September 28, 2020, through 6 pm Friday, October 2, 2020.

  • Full closure of southbound Crenshaw Bl between Brynhurst Av and 48th St.
  • Full closure of 48th St between Victoria Av and the Metro grade crossing.
  • Northbound traffic on Crenshaw Bl will remain open.

Phase 1: Southbound Vehicular & Bus Detours

  • East on Vernon Av
  • South on Western Av
  • West on Slauson Av
  • South on Crenshaw Bl

Phase 2: Starting 6 am Monday, October 5, 2020, through 6 pm Friday, October 9, 2020.

  • Full closure of northbound Crenshaw Bl between 48th St and 46th St.
  • Full closure of westbound 48th St between 11th Av and Crenshaw Bl.
  • Southbound traffic on Crenshaw Bl will remain open.

Phase 2: Northbound Vehicular & Bus Detours

  • East on Slauson Av
  • North on Western Av
  • West on Vernon Av
  • North on Crenshaw Bl

-Driveway access may be restricted.
-Access to emergency responders will be maintained.