Skip to Content

Civil Work Improvements on La Colina Dr

SUMMARY

As part of the Crenshaw/LAX Transit Project, Metro’s contractor, Walsh-Shea Corridor Constructors (WSCC) will be working on civil improvements along La Colina Dr, on Metro right-of-way. The civil work will include curb and gutter reconstruction, driveway improvements, and landscaping.

ESSENTIALS

WHAT: Civil Work Improvements
WHEN: Continuing April 3, 2021, through June 3, 2021. 6 am to 5 pm Monday through Sunday, excluding holidays. Weather permitting.
WHERE: La Colina Dr
DURATION: Two months

What to Expect

  • Lane closures adjacent to the construction activity on La Colina Dr
  • Access to emergency responders will be maintained.