Signage Installation at Artesia, Anaheim and Willow Stations

Summary 

As part of work on Metro’s New Blue Improvements Project, Metro’s contractor, RailWorks, will be removing footings and installing signage at the following stations:

  • Artesia Station
  • Anaheim Station
  • Willow Station

This installation will take place in the stations and parking lots and there is a potential for parking to be impacted during the operation.

This activity began on Thursday, May 2, and will continue daily from 7am to 3:30pm, through Friday, May 31.

Essentials 

RailWorks, will be installing signage and removing footings at three Blue Line stations.

What to Expect 

This work will include excavation, placement of rebar cages and concrete work. There will be areas with open holes that pedestrians will have restrictions from entering. There will also be a one lane closure within these stations to stage construction equipment.

Construction is a dynamic process and information is subject to change. Work activity is subject to weather conditions.

Contact Us

Metro invites you to stay involved and share your feedback. 
For questions please contact us at: 213.418.3039 or newblue@metro.net