Skip to Content

Equipment Mobilization and Pile Installation

SUMMARY

Regional Connector Constructors (RCC) will mobilize a drill rig into the Historic Broadway Station on Friday, October 15, 2020. RCC will continue pile installation within the yard as early as Saturday, October 16, 2020. Anticipated work hours are Monday through Friday from 7 am to 3:30 pm and Saturdays from 8 am to 6 pm for approximately one week.

 

ESSENTIALS

Activities include: excavation, surveying of existing underground utilities, drilling/setting piles within the construction yard, and backfilling. Access to adjacent businesses will be maintained at all times.

 

WHAT TO EXPECT

Activities will take place within construction yard on the east end of the yard.  No additional traffic closures needed.