Drainage Repair

Summary 

Regional Connector Constructors will be repairing a storm drain on the east side of Flower St, between 5th and 6th Street.

Work is anticipated to take place on Friday, August 16th, 2019 and continue for four days. 

Anticipated work hours, weather permitting, are Friday and Saturday, 9 am to 4 pm. 

Driveway closure hours are Friday, 9 am to Monday, 7 am.

Essentials 

Activities include saw cutting, grinding, pavement removal, excavation, pipe repair, backfilling, and pavement installation.

What to Expect 

Lane reductions on Flower St between 5th St and 6th St with thru access maintained.

Left turns from southbound Flower onto eastbound 6th St will be restricted during work hours.

  • Detour: right onto westbound Wilshire Bl, right onto northbound Figueroa, right on eastbound
    6th St.

Driveway access restrictions for The Standard Hotel and Paragon Parking will be in place from Friday morning to Monday morning. Access will be rerouted to the
S Hope St driveway entrance.

Noteworthy

Support local businesses! Businesses are open during construction. Take the pledge to Eat, Shop, Play DTLA/Little Tokyo at metro.net/eatshopplay.