Duct Bank Installation at Slauson Av and Crenshaw Bl

Summary

As part of Metro’s Crenshaw/LAX Transit Project, Walsh-Shea Corridor Constructors (WSCC) will be working on the installation of the duct bank at Slauson Av and Crenshaw Bl intersection. This work will be done in three phases and each phase will last approximately two weeks.

Essentials

WHAT: Duct bank installation
WHEN: Starting on May 7, 2018, from 9 pm to 6 am Monday through Friday. 8 pm to 6 am Saturday and Sunday. Weather permitting.
WHERE: Slauson Av and Crenshaw Bl
DURATION: Six weeks

What To Expect

Phase I
- All left turns will be restricted at the Slauson Av and Crenshaw Bl intersection.
- Eastbound traffic will be pushed slightly north (into left turn pockets) to accommodate for the work taking place at the southern side of the Slauson Av and Crenshaw Bl intersection.
- Access to both eastbound and westbound traffic will be maintained.
- Closure of the Crenshaw Bl crosswalk on the south side of Slauson Av. Pedestrians will be redirected to the northern crosswalk.

Phase II
- All left turns will be restricted at the Slauson Av and Crenshaw Bl intersection.
- Westbound traffic will be pushed slightly south (into left turn pockets) to accommodate for the work taking place at the northern side of the Slauson Av and Crenshaw Bl intersection.
- Access to both eastbound and westbound traffic will be maintained.
- Closure of the Crenshaw Bl crosswalk on the north side of Slauson Av. Pedestrians will be redirected to the southern crosswalk.

Phase III
- One westbound and eastbound lane reduction on Slauson Av between Victoria Av and 11th Av.
- All left turns will be restricted at the Slauson Av and Crenshaw Bl intersection.

  • Access to emergency responders will be maintained.

_____________________________________________________________________________________

Contact Us

Phone: 213.922.2736
E-mail: crenshawcorridor@metro.net
Facebook | Twitter

_____________________________________________________________________________________

Eat Shop Play Local

Project Safety

Business Interruption Fund

Metro's Business Interruption Fund (BIF) provides financial assistance to qualifying small “mom and pop” businesses directly impacted by construction; learn more by visiting metro.net/bif.  To apply, visit Metro’s program administrator, Pacific Coast Regional Small Business Development Corporation (PCR).

Metro Access

Our construction may have relocated your bus stop, or changed your route. For information changes to Metro service, please call 323.GoMetro (323.466.3876) or visit our service advisories website:

Share this page on
Advertisement
Close Search Window

Search metro.net, The Source, and El Pasajero