Weekend Closures of Flower St/6th St for Pile & Deck Installation

Summary

Regional Connector Constructors (RCC) will perform piling and decking operations on Flower St between 5th St and Wilshire Bl.

This work will require full street closures over the course of 14 weekends, starting Friday, July 6, 2018. Work hours, weather permitting, are Fridays at 8 pm to the following Monday at 5 am.

Start

Closure

Start

Closure

July 6

B

August 31

Off

July 13

A

September 7

B

July 20

A

September 14

B

July 27

A

September 21

C

August 3

A

September 28

Off

August 10

A

October 5

C

August 17

B

October 12

C

August 24

B

October 19

C


Stay up-to-date on project info—subscribe to our newsletter!

Sign up to receive the latest project news, community info and more, straight to your inbox. Subscribe now.


Essentials

Local access to businesses will be maintained. Pedestrian access will be maintained outside the construction area.

What to Expect

Closure A: Flower St between 5th St & 6th St, I-110 off-ramps at 6th St

  • Right turn maintained from 6th St to Flower St
  • I-110 detoured to Upper 4th St and 9th St
  • Use of Grand Av and Wilshire Bl recommended

Closure B: Flower St between 6th St and Wilshire Bl, I-110 off-ramps at 6th St

  • One 6th St thru-lane maintained
  • I-110 detoured to Upper 4th St and 9th St
  • Use of S Hope St recommended

 Closure C: Flower St between 6th St and Wilshire Bl

  • All 6th St thru-traffic maintained
  • I-110 6th St off-ramps open
  • Use of S Hope St recommended