Utility Investigation

SUMMARY

Metro’s contractor, Regional Connector Constructors (RCC), will conduct utility investigation to survey existing underground utility lines within the Division 20 yard.

Work is anticipated to continue Monday, August 3, 2020 through Wednesday, August 5, 2020

 

ESSENTIALS

Activities include saw cutting, excavation, surveying of existing underground utilities, and backfilling.

 

RCC will install conduit/cables for future maintenance of rail communications for the Regional Connector Project. This work is being done to maintain the L (Gold) Line in operation during a planned service interruption in Fall 2020.

 

WHAT TO EXPECT

Access to all adjacent businesses will be maintained at all times.

 Pedestrian access will be maintained outside of the work zone

 

NOTEWORTHY

22-month L (Gold) Line service interruption from Union Station, Little Tokyo/Arts District, and Pico/Aliso is anticipated to start Fall 2020. A replacement bus service will be made available by Metro.