Environmental Overview

An Environmental Impact Report (EIR) and an Environmental Impact Statement (EIS) are being prepared pursuant to the California Environmental Quality Act (CEQA) and the National Environmental Policy Act (NEPA) to comply with state and federal environmental requirements, respectively. The Link US Draft Environmental Impact Report (EIR) is available for public review from January 17 to March 4, 2019. See Meetings tab for more information regarding the public hearing and release of the Draft EIR.

There are three alternatives under study: a Proposed Project, a Build Alternative, and a No Project/No Build Alternative.

1. Proposed Project

  • Up to 10 run-through tracks over US-101
  • High-Speed Rail trains would operate on two shared lead tracks with Regional/Intercity trains
  • One new additional lead track in the “Throat” area (six lead tracks total)
  • Above-grade passenger concourse with new expanded passageway

Proposed Project

2. Build Alternative

  • Up to 10 run-through tracks over US-101
  • High-Speed Rail trains would operate on separate (dedicated) lead tracks
  • Two new additional lead tracks in the “Throat” area (seven lead tracks total)
  • At-grade passenger concourse

Build Alternative - Up to 10 New Run-Through Tracks with Shared Tracks

3. No Project/No Build Alternative

  • Assumes LAUS and the existing stub-end tracks remain as-is.

Link US Project Development Overview

The Link US project is in the early planning stages. We are currently preparing environmental studies and conceptual engineering for the project. Completion of the design will take place once the project is environmentally cleared to proceed into the final design stage. Ongoing public engagement will occur within each phase.

Anticipated Project Development Process

  • Early Planning
  • Draft Environmental Studies and Conceptual Engineering (current status)
  • Final Environmental Clearance
  • Final Design
  • Construction
  • Open for Service

Environmental Schedule

Sign up to receive project updates

Stage 1 Spring 2016 Notice of Preparation
30-Day Public Scoping Period
Public Scoping meeting
Stage 2 Spring 2016 - Fall 2018 Detailed project description
Technical studies
Stage 3 Winter - Spring 2019 Draft Environmental Impact Report (EIR)
45-day Public Comment Period (January 17 to March 4, 2019)
Public Hearing: Tuesday, January 29, 2019 6-8pm (Metro Headquarters, Board Room, 3rd Floor)
Stage 4 Summer 2019 Final Environmental Document
Board certification

Thank you for your interest in the Link Union Station Project!

The Los Angeles County Metropolitan Transportation Authority (Metro) appreciates your input in this early phase of the project development process. We are grateful for your involvement and comments as we determine the best Project for our customers, regional transit riders and the communities we serve. Thank you again for your input and we look forward to continuing the conversation as we work together to transform LAUS into a world-class station.

We Want Your Input on the Link Union Station Project!

The Draft Environmental Impact Report (EIR) is now available for public review from January 17 to March 4, 2019.

The California Environmental Quality Act (CEQA) requires a 45-day public review period of the Draft EIR to allow the public opportunity to review and provide comments on the Draft EIR. Responses to all written comments received during the 45-day public review period will be provided in the Final EIR. See the Meetings tab for more information on the public hearing and public review process.