FTIP

The Transportation Improvement Plan (TIP) is a federally mandated listing of transportation projects that will be funded with federal, state or local funds over the next four years. The TIP includes regionally significant and/or federally funded transit, highway, local roadway, bridge, freight, bicycle, and pedestrian capital and non-capital projects.  All transportation projects must be listed in an approved TIP in order to access federal or state funding

In Los Angeles County, local agencies program new and revised transportation projects using the Program Metro platform . Once submitted, projects are reviewed for compliance with federal and state laws and for fiscal constraint first by Metro, then SCAG, before being submitted to the California Department of Transportation (Caltrans), and the U.S. Department of Transportation (USDOT).

The FTIP is adopted once every odd year (2013, 2015, 2017, 2019 etc.). Effective December 2018, the 2019 FTIP will replace the 2017 FTIP.

Amending the TIP - Amendments and Administrative Modifications

On an alternating monthly basis, agencies are given the opportunity to introduce or update projects on ProgramMetro. Projects may be created or amended through either a Formal Amendment or and Administrative Modification. Please note that for project amendments to be approved by SCAG, the changes must meet the following criteria:

  • May not affect the regional emissions analysis
  • May not affect the timely implementation of the Transportation Control Measures
  • May not adversely impact financial constraint
  • Stay consistent with the adopted Regional Transportation Plan (RTP)

Administrative Modification
This procedure is for minor changes to project cost, schedule, scope, or funding sources. Administrative Modifications are usually approved 30 days SCAG has the delegated authority to approve administrative modifications, so this process is much quicker than the amendment

Formal Amendment
This procedure is for changes of larger significance. Because of the many layers of review, Formal Amendments can take up to 3 months for approval. Changes that qualify for a Formal Amendment include

  1. cost changes that are greater than 40 percent of the total project cost or $10 million, whichever is higher
  2. adding or deleting projects that are exempt from regional emission analyses
  3. adding a project or a project phase to the program
  4. significant changes to the design concept, scope, or schedule of an existing project

For a complete definition of eligible changes, please see Section VII. Amendments and Administrative Modifications .

ProgramMetro

ProgramMetro is Los Angeles County's online TIP database. It eliminates the need for manual project submissions and ensures that both Metro and lead agencies have access to the most up-to-date entries. Agencies must view, edit, and submit their transportation projects into the TIP through ProgramMetro. Metro will not carry out the submission process on the agencies behalf. To access the Program Metro funding system please use the link below.

https://programmetro.ecointeractive.com/secure/login

TIP Workshops

The Metro TIP team regularly offers informational workshops for agency staff to explain the TIP process, its significance, and how it fits in the agency’s overall project delivery plan. These hands-on workshops also allow agency staff an opportunity to learn the different features of ProgramMetro.

To register for the upcoming TIP workshop, please contact Robin Franke at franker@metro.net .

Contact Us

Nancy Marroquin - marroquinn@metro.net
Doreen Morrissey - morrisseyd@metro.net
Nick Zhao - zhaoji@metro.net
Robin Franke - franker@metro.net

Advertisement
Close Search Window

Search metro.net, The Source, and El Pasajero