Date Notice Brief Detail

October 15

Equipment Mobilization and Pile Installation

Teaser text

More information about Equipment Mobilization and Pile Installation in HTML format

October 04

Historic Broadway Station Street Restoration

Regional Connector Constructors (RCC) will implement an extended closure of 2nd St between Spring St and Broadway for deck removal and street restoration as early as October 30, 2020 through Summer 2021. 

More information about Historic Broadway Station Street Restoration in HTML format

September 25

Pile Installation for Pedestrian Bridge

Regional Connector Constructors (RCC) will implement a full weekend traffic closure on Hope St for pile installation in support of the future pedestrian bridge connecting the future Grand Av Arts/Bunker Hill Station to The Broad.

More information about Pile Installation for Pedestrian Bridge in HTML format

September 23

Civil Restoration and Waterline Relocation

Waterline relocation is anticipated through October 21, 2020.

More information about Civil Restoration and Waterline Relocation in HTML format

September 12

Utility Maintenance Hole Investigation

Regional Connector Constructors (RCC) will implement a traffic restriction on westbound 5th St for utility backfill operations investigation within a utility maintenance hole.

More information about Utility Maintenance Hole Investigation in HTML format

September 11

Sewer Line Installation

Regional Connector Constructors (RCC) will continue the installation of a sewer line on Temple St between Alameda and Garey St. Work continues Monday, September 28, 2020 and continues for approximately five months. Anticipated work hours are Monday through Friday,  7 pm to 4 am.

More information about Sewer Line Installation in HTML format

August 28

道路修復工事 及び閉鎖

Regional Connector Constructors (RCC) は道路修復工事のためにCentral Avの 1st St 及び 2nd St間の閉鎖の延長を実施します。この毎日全日終夜[1] の 閉鎖は2020年の8月28日に開始され約8週間継続します。

More information about 道路修復工事 及び閉鎖 in HTML format

August 28

Central Av Restoration

Regional Connector Constructors (RCC) will implement an extended closure of Central Av between 1st St and 2nd St for street restoration. Work is anticipated to continue through 2020. Anticipated work hours, weather permitting, are 6 am to 4:30 pm, Monday through Saturday. Sunday work will be scheduled as needed.

More information about Central Av Restoration in HTML format
More information about Central Av Restoration in PDF format

August 26

Utility Investigation

Regional Connector Constructors (RCC) will conduct utility investigation at Hope St between 2nd St and GTK Way. Work is anticipated to begin as early as Wednesday, August 26, 2020, and continue for approximately two weeks. Anticipated work hours will be from 9 am to 3:30 pm Monday through Friday, and Saturday from 8 am to 6 pm. Activities will include set up for traffic, saw cutting, breaking up of concrete, excavating, utility investigation, placing backfill material, and paving.

More information about Utility Investigation in HTML format

August 01

Fall 2020 Regional Connector

The Little Tokyo/Arts District Metro Transit Station will be demolished, and replaced with a new station, located on the Regional Connector alignment.

More information about Fall 2020 Regional Connector in HTML format

July 20

Utility Investigation

Metro’s contractor, Regional Connector Constructors (RCC), will continue utility investigation to survey existing underground utility lines within the Division 20 yard and on 1st St between Mission Rd and Vignes St.

Additional night work may be scheduled at a later date for proposed work at the 1st St Bridge. A supplemental notice will be issued once work is scheduled.

More information about Utility Investigation in HTML format

July 17

Fire Hydrant and Waterline Installation

RCC will install a new fire hydrant and waterline at the southeast corner of 1st St and Central Av.

More information about Fire Hydrant and Waterline Installation in HTML format

June 04

Storm Drain Installation

Regional Connector Constructors (RCC) will continue the installation of a storm drain line on Temple St between Alameda and Garey St. Work is anticipated to begin Thursday, June 24, 2020, and continue for approximately one month. Anticipated work hours will be Monday through Saturday from 6 am to 6 pm.

More information about Storm Drain Installation in HTML format

May 30

Utility Investigation

Regional Connector Constructors (RCC) will conduct utility investigation at the 2nd St and Broadway intersection.  Anticipated work hours will be Saturdays from 8 am to 6 pm and Sundays from 8 am to 9 pm.

More information about Utility Investigation in HTML format

May 21

Alameda guideway excavation at Mangrove Yard

Regional Connector Constructors (RCC) will be performing excavation activities for the Alameda guideway within the Mangrove Yard.

More information about Alameda guideway excavation at Mangrove Yard in HTML format

May 07

Waterline Excavation on westbound 1st St between Vignes St and Alameda St

Regional Connector Constructors (RCC) will begin excavating and securing underground utilities for a new 12” waterline on westbound 1st between Vignes St and Alameda St. This work is building the utility infrastructure only and no service interruptions are anticipated.
Work is anticipated to begin Thursday, May 7, 2020, and continue for approximately two weeks.
Anticipated work hours will be from 9 am to 3 pm, Monday through Saturday.

More information about Waterline Excavation on westbound 1st St between Vignes St and Alameda St in HTML format

April 20

Central Ave Pile Excavation

RCC will continue excavation along the east side of Central Av between 1st St and 2nd St for construction of a tunnel vent. A curb lane closure along the 1st/Central station will be in place during work hours.  Pile installation is anticipated to continue through July 31, 2020. Work hours are from 6 am to 6 pm Monday through Saturday.

More information about Central Ave Pile Excavation in HTML format

April 20

Backfill Material Delivery on Flower St

Regional Connector Constructors will begin the delivery of backfill material on Flower St, between 4th and 5th St.

More information about Backfill Material Delivery on Flower St in HTML format

April 01

Backfill Material Delivery on Flower St

Regional Connector Constructors will begin delivery of backfill material on Flower St, between 4th and 5th St.

More information about Backfill Material Delivery on Flower St in HTML format

January 13

Southern California Gas Line Installation

Utility installation by Southern Califonia Gas Company in downtown LA

More information about Southern California Gas Line Installation in HTML format

January 10

Street Restoration at 1st St and Alameda St

RCC will continue the extended closure of the 1st St and Alameda St intersection for street restoration. A 24/7 closure is anticipated to continue until Monday, August 31, 2020. 

More information about Street Restoration at 1st St and Alameda St in HTML format

October 04

Construction activities on Flower St

Construction activities on Flower St in downtown LA

More information about Construction activities on Flower St in HTML format

May 01

Street Closures and Detours

Review the real-time map and longer term street impacts.

More information about Street Closures and Detours in HTML format

January 01

1st およびセントラルステーションでのコンクリート打設

1st およびセントラルステーションでのコンクリート打設

More information about 1st およびセントラルステーションでのコンクリート打設 in HTML format

January 01

1번가와 중앙역에서 콘크리트 타설

1번가와 중앙역에서 콘크리트 타설  

More information about 1번가와 중앙역에서 콘크리트 타설 in HTML format

January 01

Colocación del concreto en la estación de la 1st y Central

Colocación del concreto en la estación de la 1st y Central  

More information about Colocación del concreto en la estación de la 1st y Central in HTML format

December 05

Bikes prohibited on westbound 1st St, between Vignes and Alameda St, through 2021

Bikes prohibited on westbound 1st St, between Vignes and Alameda St, through 2021

More information about Bikes prohibited on westbound 1st St, between Vignes and Alameda St, through 2021 in HTML format

September 14

Concrete placement on Flower St

Concrete placement for the connection into 7th/Metro Center

More information about Concrete placement on Flower St in HTML format

May 23

1st and Central Concrete Placement

Concrete placement for the Little Tokyo/Arts District station

More information about 1st and Central Concrete Placement in HTML format

May 07

Concrete Placement at the Historic Broadway Station

Concrete placement for the Historic Broadway Station

More information about Concrete Placement at the Historic Broadway Station in HTML format

August 04

Construction Activities at the 2nd/Hope Station Yard

Regional Connector Constructors (RCC) will continue to perform construction activities at the 2nd/Hope Station Yard. Work is anticipated to continue through Summer 2021.

More information about Construction Activities at the 2nd/Hope Station Yard in HTML format

June 08

Bus Stop Relocation at 3rd St/Flower St

Beginning Monday, June 8, 2015 the bus stop at the 3rd St/Flower St intersection will be relocated to the south east corner of 3rd St/Hope St.

More information about Bus Stop Relocation at 3rd St/Flower St in HTML format
More information about Bus Stop Relocation at 3rd St/Flower St in PDF format