Skip to Content
Search

Regional Connector Transit Project

Construction Notices

Get construction updates on Twitter

Date Notice Brief Detail

June 03

Closure of 6th St at I-110 Freeway

6th St closure

More information about Closure of 6th St at I-110 Freeway in HTML format

May 08

Storm Drain Installation on 2nd St. between Broadway and Spring St.

Storm drain install

More information about Storm Drain Installation on 2nd St. between Broadway and Spring St. in HTML format

April 28

Concrete Placement on Flower St. between 4th St. and 5th St.

Concrete pour

More information about Concrete Placement on Flower St. between 4th St. and 5th St. in HTML format

April 26

Geotechnical Instrumentation Installation on 5th St. between Flower & Figueroa St.

Geotech instrument install

More information about Geotechnical Instrumentation Installation on 5th St. between Flower & Figueroa St. in HTML format

April 25

Water Line Tie-in on Flower St. between 5th St. and 6th St.

Waterline tie in

More information about Water Line Tie-in on Flower St. between 5th St. and 6th St. in HTML format

April 22

Geotechnical Instrumentation Installation on Flower St.

Geotech install

More information about Geotechnical Instrumentation Installation on Flower St. in HTML format

April 20

Traffic Management Conduit Installation on Broadway St. between 1st St. & Temple St.

Conduit install

More information about Traffic Management Conduit Installation on Broadway St. between 1st St. & Temple St. in HTML format

April 17

Traffic Management Conduit Installation on Broadway, between 1st and 2nd St.

Conduit installation

More information about Traffic Management Conduit Installation on Broadway, between 1st and 2nd St. in HTML format

April 10

Utility Investigation on the East side of Central Ave. between 1st St. and 2nd St.

Utility investigation

More information about Utility Investigation on the East side of Central Ave. between 1st St. and 2nd St. in HTML format

April 10

Geotechnical Instrumentation Installation on Flower St. between 3rd St. and 4th St

Geotech install

More information about Geotechnical Instrumentation Installation on Flower St. between 3rd St. and 4th St in HTML format

April 10

Construction Activities at the 2nd/Hope Yard

Construction activities

More information about Construction Activities at the 2nd/Hope Yard in HTML format

April 08

Sawcutting on Flower St and Hope St

Sawcutting

More information about Sawcutting on Flower St and Hope St in HTML format

April 07

Asphalt Pavement Repair at 1st St. and Garey St.

Pavement repair

More information about Asphalt Pavement Repair at 1st St. and Garey St. in HTML format

April 07

Geotechnical Instrumentation Installation at 3rd St. and Flower St. Intersection

Geotech instrument install

More information about Geotechnical Instrumentation Installation at 3rd St. and Flower St. Intersection in HTML format

April 03

Construction Fence on Pedestrian Sidewalk- Eastside Flower St. and 5th St

Construction fence placement

More information about Construction Fence on Pedestrian Sidewalk- Eastside Flower St. and 5th St in HTML format

April 01

Geotechnical Instrumentation Installation & Maintenance at 2nd St. & Hill St. Intersection

Geotech instrument install

More information about Geotechnical Instrumentation Installation & Maintenance at 2nd St. & Hill St. Intersection in HTML format

March 28

Geotechnical Instrumentation Installation at 3rd St and Flower St. Intersection

Geotech install

More information about Geotechnical Instrumentation Installation at 3rd St and Flower St. Intersection in HTML format

March 25

Paving at the Intersection of 6th St and Flower St

Paving

More information about Paving at the Intersection of 6th St and Flower St in HTML format

March 24

Tunnel Mining

Tunnel mining

More information about Tunnel Mining in HTML format

March 20

Geotechnical Instrument Installation on Hope St. between 2nd St. & GTK Way

Geotech install

More information about Geotechnical Instrument Installation on Hope St. between 2nd St. & GTK Way in HTML format

March 20

Historic Broadway Parking Validation Program

Two hour free parking

More information about Historic Broadway Parking Validation Program in HTML format

March 18

Paving at 2nd St. & Hill St. Intersection

Paving

More information about Paving at 2nd St. & Hill St. Intersection in HTML format

March 18

Asphalt Pavement Repair at 1st St. & Garey St.

Pavement repair

More information about Asphalt Pavement Repair at 1st St. & Garey St. in HTML format

March 17

Geotechnical Instrumentation Installation on Flower St.

Instrument installation

More information about Geotechnical Instrumentation Installation on Flower St. in HTML format

March 11

Utility Investigation & Geotechnical Installation at the Intersection of 2nd St. and Hill St.

Utility investigation

More information about Utility Investigation & Geotechnical Installation at the Intersection of 2nd St. and Hill St. in HTML format

March 09

Pothole Repair Activity at 1st St. and Garey St.

Pothole repair

More information about Pothole Repair Activity at 1st St. and Garey St. in HTML format

March 06

Noise barrier install at the 1st/Central Station site

Noise barrier installation

More information about Noise barrier install at the 1st/Central Station site in HTML format

March 06

Excavation Continues on Flower St. between 4th St. and 5th St.

Excavation

More information about Excavation Continues on Flower St. between 4th St. and 5th St. in HTML format

March 01

Utility Investigation on Flower St, between 5th St & 6th St

Utility investigation

More information about Utility Investigation on Flower St, between 5th St & 6th St in HTML format

February 27

Sound Wall Installation on Spring St.

Building noise barrier

More information about Sound Wall Installation on Spring St. in HTML format

February 25

Geotechnical Installation at the Intersection of 2nd/Hill St.

Geotech installation

More information about Geotechnical Installation at the Intersection of 2nd/Hill St. in HTML format

February 25

Equipment Maintenance Activity at 1st and Alameda St

Instrument maintenance

More information about Equipment Maintenance Activity at 1st and Alameda St in HTML format

February 20

Power Relocation Activities on Flower St, between 5th St and Wilshire Blvd

Power relocation

More information about Power Relocation Activities on Flower St, between 5th St and Wilshire Blvd in HTML format

February 15

Waterline Relocation on Flower St between 5th St and 6th St

Waterline relocation

More information about Waterline Relocation on Flower St between 5th St and 6th St in HTML format

February 14

Restoration Activities at 3rd St. and Flower St.

Street restoration

More information about Restoration Activities at 3rd St. and Flower St. in HTML format

February 14

Concrete Placement at the 2nd/Hope Station

Concrete slab placement

More information about Concrete Placement at the 2nd/Hope Station in HTML format

February 06

Utility Investigation at 2nd St & Hill St Intersection

Utility investigation

More information about Utility Investigation at 2nd St & Hill St Intersection in HTML format

February 06

Weekday Excavation on Flower St between 4th St and 5th St

Excavation

More information about Weekday Excavation on Flower St between 4th St and 5th St in HTML format

February 01

Restoration Activities on 2nd St. between Central Ave. and San Pedro St.

Restoration activities

More information about Restoration Activities on 2nd St. between Central Ave. and San Pedro St. in HTML format

January 28

Paving at the 6th St./Flower St. Intersection

Street paving

More information about Paving at the 6th St./Flower St. Intersection in HTML format

January 26

Geotechnical Communication Barrel Installation on 2nd St between San Pedro St & Main St

Geotech install

More information about Geotechnical Communication Barrel Installation on 2nd St between San Pedro St & Main St in HTML format

January 23

Geotechnical Instrumentation Installation on Flower St

Geotech instrument install

More information about Geotechnical Instrumentation Installation on Flower St in HTML format

January 19

Piling activities at the intersection of 5th St and Flower St

Piling activities

More information about Piling activities at the intersection of 5th St and Flower St in HTML format

January 18

Geotechnical Instrumentation Install on 2nd St. between Hill St. & and Broadway St.

Geotech instrumentation

More information about Geotechnical Instrumentation Install on 2nd St. between Hill St. & and Broadway St. in HTML format

January 17

CCTV Utility Surveying on 2nd St. between Central Ave. and Main St.

Utility surveying

More information about CCTV Utility Surveying on 2nd St. between Central Ave. and Main St. in HTML format

January 14

Geotech Instrument Installation on 5th St, between Flower St and Figueroa St

Geotech instrumenation

More information about Geotech Instrument Installation on 5th St, between Flower St and Figueroa St in HTML format

January 13

Landscape Maintenance at the Gold Line’s Little Tokyo Station

Landscaping

More information about Landscape Maintenance at the Gold Line’s Little Tokyo Station in HTML format

January 12

Geotechnical Instrumentation Installation on Flower St. between 5th St. and 6th St.

Geotech installation

More information about Geotechnical Instrumentation Installation on Flower St. between 5th St. and 6th St. in HTML format

January 11

Tree Removal in the Vicinity of 2nd/Hope & Flower/Financial District Station Sites

Tree removal

More information about Tree Removal in the Vicinity of 2nd/Hope & Flower/Financial District Station Sites in HTML format

January 10

Power Relocation Activities on Flower St. between 6th St. and Wilshire Bl.

Power relocation

More information about Power Relocation Activities on Flower St. between 6th St. and Wilshire Bl. in HTML format

January 09

Geotechnical Instrumentation Install at the Intersection of 2nd/Broadway

Geotech install

More information about Geotechnical Instrumentation Install at the Intersection of 2nd/Broadway in HTML format

January 09

Geotechnical Instrumentation Install at the Intersection of 2nd St. & San Pedro St.

Geotech install

More information about Geotechnical Instrumentation Install at the Intersection of 2nd St. & San Pedro St. in HTML format

January 07

Water Relocation at the 6th St. and Flower St. Intersection

Water relocation

More information about Water Relocation at the 6th St. and Flower St. Intersection in HTML format

January 03

Potholing Activity on Flower St. South of 6th St.

Potholing

More information about Potholing Activity on Flower St. South of 6th St. in HTML format

December 23

CCTV main sewer line along 2nd St. at 2nd St. and Los Angeles St.

CCTV sewer line 

More information about CCTV main sewer line along 2nd St. at 2nd St. and Los Angeles St. in HTML format

December 23

Geotechnical Inst. Installation on 2nd St. between Main St. and Spring St.

Installing geotech instrumentation

More information about Geotechnical Inst. Installation on 2nd St. between Main St. and Spring St. in HTML format

December 21

Street Restriping on Spring St. between 1st St. and 2nd St.

Restriping

More information about Street Restriping on Spring St. between 1st St. and 2nd St. in HTML format

December 13

Geotech Instrument Installation on the west side of Flower St. between 3rd St. & 4th St.

Geotech install

More information about Geotech Instrument Installation on the west side of Flower St. between 3rd St. & 4th St. in HTML format

December 12

Utility Investigation at 5th St./Flower St. Intersection to 6th St.

Utility investigation

More information about Utility Investigation at 5th St./Flower St. Intersection to 6th St. in HTML format

December 10

Paving 5thSt./Flower St. Intersection to 6th St./Flower St. Mid-Block

Paving 

More information about Paving 5thSt./Flower St. Intersection to 6th St./Flower St. Mid-Block in HTML format

December 05

Geotechnical Inst. Installation on 2nd St. between Hill St. & Broadway

Installing geotech instrumentation

More information about Geotechnical Inst. Installation on 2nd St. between Hill St. & Broadway in HTML format

December 05

Geotechnical Inst. Installation on 2nd St. between Main St. and Spring St.

Installing geotech instrumentation

More information about Geotechnical Inst. Installation on 2nd St. between Main St. and Spring St. in HTML format

December 03

Full Weekend Closure of 2nd St./Spring St. Intersection

Spring St decking

More information about Full Weekend Closure of 2nd St./Spring St. Intersection in HTML format
More information about Full Weekend Closure of 2nd St./Spring St. Intersection in PDF format

December 03

Aviso de cierre completo de la intersección de 2nd/Spring St. Sábado, 3 de diciembre de 2016 - solo un día

Cierre completo de la intersección de 2nd/Spring St

More information about Aviso de cierre completo de la intersección de 2nd/Spring St. Sábado, 3 de diciembre de 2016 - solo un día in HTML format
More information about Aviso de cierre completo de la intersección de 2nd/Spring St. Sábado, 3 de diciembre de 2016 - solo un día in PDF format

December 03

Waterline Preparation Activity at the 6th St./Flower St. Intersection

Sawcutting

More information about Waterline Preparation Activity at the 6th St./Flower St. Intersection in HTML format

November 28

在 San Pedro St. 附近 2nd St. 進行岩土工程儀器安裝

Regional Connector Constructors(RCC)將在 Central Ave. 與 San Pedro St. 之間的西向 2nd St. 路段安裝岩土工程儀器。

More information about 在 San Pedro St. 附近 2nd St. 進行岩土工程儀器安裝 in HTML format

November 28

Regional Connect Constructors (RCC) では2nd St.のSan Pedro St.~Central Ave.の西行き側に地盤計測装置を設置します。

この作業は2016年11月28日から
2週間にわたって行われます。

More information about Regional Connect Constructors (RCC) では2nd St.のSan Pedro St.~Central Ave.の西行き側に地盤計測装置を設置します。 in HTML format

November 28

Geotechnical Instrumentation Installation on 2nd St. near San Pedro St.

Geotech install

More information about Geotechnical Instrumentation Installation on 2nd St. near San Pedro St. in HTML format

November 28

Instalación de instrumentación geotécnica en 2nd St cerca de San Pedro St

Regional Connector Constructors (RCC) instalará la instrumentación geotécnica en 2nd St en dirección oeste entre Central Ave y San Pedro St.

More information about Instalación de instrumentación geotécnica en 2nd St cerca de San Pedro St in HTML format

November 28

산페드로 스트리트에 인접한 2번가에 지반 계측 장비 설치

Regional Connector Constructors (RCC)는 센트럴 애비뉴와 산페드로 스트리트 사이의 서쪽 방향 2번가에 지반 계측 장비를 설치할 예정입니다.

More information about 산페드로 스트리트에 인접한 2번가에 지반 계측 장비 설치 in HTML format

November 21

Geotechnical Instrumentation Installation on the west side of Alameda St.

Geotech install

More information about Geotechnical Instrumentation Installation on the west side of Alameda St. in HTML format

November 21

Geotechnical Instrumentation Installation on 2nd St. between Los Angeles St. & Main St.

Geotech install

More information about Geotechnical Instrumentation Installation on 2nd St. between Los Angeles St. & Main St. in HTML format

November 19

Street Paving Activity in the Vicinity of 6th St. & Flower St. Intersection

Street paving

More information about Street Paving Activity in the Vicinity of 6th St. & Flower St. Intersection in HTML format

November 16

Geotechnical Instrumentation Installation on Central Ave. between 1st St. & 2nd St.

Geotech instrument install

More information about Geotechnical Instrumentation Installation on Central Ave. between 1st St. & 2nd St. in HTML format

November 16

Potholing activities on Flower St., south of 6th St

Underground utility investigation

More information about Potholing activities on Flower St., south of 6th St in HTML format

November 14

Waterline Work Preparation Activity on Flower St. between 6th St. & Wilshire Blvd.

Sawcutting on Flower St

More information about Waterline Work Preparation Activity on Flower St. between 6th St. & Wilshire Blvd. in HTML format

November 14

Construction Activities 1st/Alameda Behind K-rails

Continued pile installation

More information about Construction Activities 1st/Alameda Behind K-rails in HTML format

November 14

Tunnel Boring Machine (TBM) Assembly Activities at the Mangrove Yard

TBM delivery and assembly

More information about Tunnel Boring Machine (TBM) Assembly Activities at the Mangrove Yard in HTML format

November 05

Preparation for Waterline Work on Flower St. between 5th St. and Wilshire Blvd.

Sawcutting for future waterline work

More information about Preparation for Waterline Work on Flower St. between 5th St. and Wilshire Blvd. in HTML format

November 05

Concrete Placement in the 1st St. & Alameda St. Cut-and-Cover Tunnel

Concrete slab placement

More information about Concrete Placement in the 1st St. & Alameda St. Cut-and-Cover Tunnel in HTML format

November 03

Removal of an Abandoned Power Duct Bank at the Intersection of 4th St. & Flower St.

Removal of existing power duct bank

More information about Removal of an Abandoned Power Duct Bank at the Intersection of 4th St. & Flower St. in HTML format

November 02

Geotechnical Instrumentation Installation on 2nd St. between San Pedro St. & Los Angeles St.

Geotechnical instrument install

More information about Geotechnical Instrumentation Installation on 2nd St. between San Pedro St. & Los Angeles St. in HTML format

October 29

DWP Power Intercept and Street Restoration on the south side of 5th St., west of Flower St.

Utility relocation and street restoration

More information about DWP Power Intercept and Street Restoration on the south side of 5th St., west of Flower St. in HTML format

October 29

Aviso de cierre completo de la intersección de 2nd/Broadway

Cierre completo

More information about Aviso de cierre completo de la intersección de 2nd/Broadway in HTML format

October 29

Full Intersection Closure at 2nd/Broadway

Intersection closures at 2nd/Broadway

More information about Full Intersection Closure at 2nd/Broadway in HTML format

October 24

Geotechnical Instrumentation Installation on the east side of Flower St, between 3rd and 4th St

Geotech install

More information about Geotechnical Instrumentation Installation on the east side of Flower St, between 3rd and 4th St in HTML format

October 14

Cierre de Flower St para instalación de plataforma 3rd St a 5th St

Flower St Decking

More information about Cierre de Flower St para instalación de plataforma 3rd St a 5th St in HTML format

October 14

Flower St. Decking, 3rd St to 5th St

Weekend closures for decking

More information about Flower St. Decking, 3rd St to 5th St in HTML format

October 14

デッキ設置による3rd St~5th St間Flower St通行止めのお知らせ

Flower St Decking

More information about デッキ設置による3rd St~5th St間Flower St通行止めのお知らせ in HTML format

October 14

3번가와 5번가 사이의 데크 설치를 위한 플라워 스트리트 폐쇄

Flower St Decking

More information about 3번가와 5번가 사이의 데크 설치를 위한 플라워 스트리트 폐쇄 in HTML format

October 10

Extended Temporary Power Installation at the 5th St. & Flower St. Intersection

Installing temporary underground power duct banks

More information about Extended Temporary Power Installation at the 5th St. & Flower St. Intersection in HTML format

September 26

Power Utility Work (LADWP) on west side of Flower St., south of 5th St.

On-going power relocation efforts

More information about Power Utility Work (LADWP) on west side of Flower St., south of 5th St. in HTML format

September 26

Street Closures and Detours

Review the real-time map and longer term street impacts.

More information about Street Closures and Detours in HTML format

August 20

Tieback Removal at 3rd St and Flower St

Construction of the tieback removal shaft 

More information about Tieback Removal at 3rd St and Flower St in HTML format

August 20

Piling and Decking Installation behind k rail at 2nd/Broadway Station

Utility relocation, piling and decking

More information about Piling and Decking Installation behind k rail at 2nd/Broadway Station in HTML format

July 23

Continuation of Excavation at 2nd and Hope Station with additional shift

Continue performing excavation

More information about Continuation of Excavation at 2nd and Hope Station with additional shift in HTML format

July 05

Site Excavation at the 2nd/Hope Yard

Continued excavation activities

More information about Site Excavation at the 2nd/Hope Yard in HTML format

June 04

Pile Installation on west side Flower St, between 4th and 5th St

Pile installation on the west side of Flower St. between 4th St and 5th.

More information about Pile Installation on west side Flower St, between 4th and 5th St in HTML format

February 27

Notice of Full Closure of 2nd/Broadway Intersection for Station Construction

Implementation of 7-month and subsequent 4-month closures.

More information about Notice of Full Closure of 2nd/Broadway Intersection for Station Construction in HTML format

February 27

Aviso de cierre total de la intersección 2nd/Broadway para construcción de estación

Cierre de la intersección 2nd/Broadway para reubicación de servicios públicos e instalación de pilotes y paneles de plataforma para apoyar la construcción de la estación en 2nd/Broadway. 

More information about Aviso de cierre total de la intersección 2nd/Broadway para construcción de estación in HTML format

February 27

역 공사를 위한 2nd/Broadway 교차로 완전 폐쇄 통지

2nd/Broadway Station 공사 지원을 위한 유틸리티 위치 변경 및 기둥과 덱 패널 설치를 위해2nd/Broadway 교차로 폐쇄   

 

More information about 역 공사를 위한 2nd/Broadway 교차로 완전 폐쇄 통지 in HTML format

June 08

Bus Stop Relocation at 3rd St/Flower St

Beginning Monday, June 8, 2015 the bus stop at the 3rd St/Flower St intersection will be relocated to the south east corner of 3rd St/Hope St.

More information about Bus Stop Relocation at 3rd St/Flower St in HTML format
More information about Bus Stop Relocation at 3rd St/Flower St in PDF format
Share this page on
Advertisement
Close Search Window

Search metro.net, The Source, and El Pasajero