1st and Central Concrete Placement

June 18 @ 4:00 am - November 5 @ 6:00 pm

Summary

Regional Connector Constructors (RCC) will be placing concrete within the future Little Tokyo/Arts District Station. Anticipated work hours, weather permitting, are 4 am to 6 pm, Monday through Friday and 8 am to 3 pm on Saturdays.

These are the upcoming dates:

  • Friday, October 15, 2021 
  • Monday, October 18, 2021
  • Tuesday, October 19, 2021 
  • Wednesday, October 20, 2021
  • Friday, October 22, 2021 
  • Wednesday, October 27, 2021
  • Friday, November 5, 2021

Concrete delivery and placement times will vary throughout the anticipated work hours.

Essentials

Activities include concrete delivery, pumping, and placement within the station limits. Sound mitigations will be in place during work hours. Pedestrian, business, and local access will be maintained.

What to Expect

Concrete trucks will enter the project site from Alameda Street and stage within the yard. Work will be behind the current k-rail. No additional closures will be required.

*Dates are subject to change.