Map Kiosk Foundation Installation

October 8 @ 9:00 am - October 15 @ 3:30 pm

|Recurring Event (See all)

An event every day that begins at 9:00 am, repeating until October 14, 2021

Summary
Metro’s contractors will perform map kiosk foundation installations as part of the Eastside Access Improvements Project.

Noteworthy

  • The construction activities include drilling and concrete restoration.
  • Parking will be reduced during construction between 2nd/3rd St.
  • Thru traffic maintained.
  • Access to pedestrians will be maintained outside of the work area. Construction equipment will be staged and demobilized from the site daily.

Essentials
The Eastside Access Improvements Project brings a wide range of improvements that safeguard pedestrian and cyclists’ movements from transit to and through Little Tokyo and the Arts District.

Improvements include various streetscape elements such as:

  • New and Improved Lighting
  • Access Ramps
  • Tree Planting
  • Kiosks/Wayfinding Signs
  • Defined Pedestrian/Bicycle Pathways and More

What to Expect
Ten (10) Map Kiosk Foundation Installations

Where: 

  • Southwest Corner: 1st St / Central Av
  • Northeast sidewalk: 2nd St / Central Av
  • Northeast sidewalk: 2nd St / Alameda Av
  • Southwest sidewalk: 1st St / Alameda Av
  • Southeast Sidewalk: 1st St / San Pedro St
  • Northwest sidewalk: 2nd St
  • Northeast sidewalk: 3rd St/ Garey St
  • Southwest sidewalk: 2nd St / 3rd St
  • Southeast sidewalk: 3rd St / Santa Fe Av
  • Southeast sidewalk: Azusa St / San Pedro St

When:
Approximately five (5) day work duration anticipated to begin as soon as Thursday, October 7, 2021.

Hours of Construction:
Monday – Friday, 9am to 3:30pm

Construction is a dynamic process and information is subject to change without notice. For questions or complaints, contact our project hotline at 213.922.1111 or email centrallaprojects@metro.net.

Details

Start:
October 8 @ 9:00 am
End:
October 15 @ 3:30 pm