Pre-restoration Work and Backfill Material Delivery on Flower St

July 7, 2021 @ 6:00 am - January 5, 2022 @ 3:30 pm

|Recurring Event (See all)

An event every week that begins at 6:00 am on Monday, Tuesday, Wednesday, Thursday and Friday, repeating until November 30, 2021

Summary

Regional Connector Constructors (RCC) will continue pre-restoration work and material delivery planned for Flower St, between 3rd St and Wilshire Bl. 

 Work hours, weather permitting, are 6 am to 3:30 pm, Monday through Friday. Saturday from 6 am to 6 pm. This notice will continue to be updated with additional pre-restoration activities as necessary.

 Essentials

Activities will include traffic control set up, equipment mobilization, curb demo, utility installation, installation of chain link fencing, and delivery/removal of backfill and materials.

  What to Expect

  • Thru traffic is maintained.
  • Intermittent lane restrictions on southbound Flower St, between 3rd and 5th St.
  • Eastbound 4th St will be reduced to a right turn only during work hours between Figueroa and Flower St.
  • Access to pedestrian walkways and nearby businesses will be maintained outside of the work area.

Details

Start:
July 7 @ 6:00 am
End:
January 5, 2022 @ 3:30 pm
Event Category: