News & Info
Where we are Now
Our consulting team, led by InfraConsult LLC, has finished the first phases of screening of a total of 81 projects, and has identified seven transit and seven highway projects as the best projects for continuing consideration for private sector participation. (Please click on the link to the Board Report dated October 14, 2009, Item 9 to see the list of 14 projects.)
Of these 14 projects, we recommend an initial six projects be considered for more in-depth strategic assessments and development of project-specific business cases. The remaining eight projects on the list could be analyzed in the future. The initial six projects are: I-710 South including the I-710 South Early Action Projects; Crenshaw Transit Corridor; SR-710 North Extension; High Desert Corridor; Regional Connector; and the Metro Red Line Westside Subway Extension: Wilshire/Western Station to Westwood via the Wilshire Boulevard alignment.
Upon Board authorization to proceed, we will be meeting with the staff and consultant teams who are currently developing the above-referenced projects, to assess project status and collaborate on aspects which could accelerate project delivery and facilitate private sector participation.
Click on the link for access to the full Project Screening Report:
Project Screening Technical Memorandum, October 9, 2009
Draft 2008 Long Range Transportation Plan
- Draft 2008 Long Range Transportation Plan Tier 1 Strategic Projects Performance Measures and Analysis(PDF format, 190 KB)
- Draft 2008 Long Range Transportation Plan project sketches and Metro system operations for consideration of Public-Private Partnership (PPP) (PDF format, 2.3MB)
Board Motions and Reports
- November 2007 Item 46
- January 2008 Item 11
- March 19, 2008 Item 13
- April 2008 Item 50
- June 2008 Item 7
- September 17, 2008 Item 6
- April 15, 2009 Item 5
- October 14, 2009, Item 9
Transit Corridor Studies