Home > Projects & Programs > Measure R > Measure R Project Tracker


Measure R Project Tracker


Project Name & Description Funding Status

Agoura Hills Multi-Modal Center

TBD

Part of the Highway Operational Improvements in Las Virgenes and Malibu Subregion

Region(s): Las Virgenes/Malibu
City: Agoura Hills
$TBD Ongoing

Arterial Capacity Enhancement and Emergency Relief Project

TBD

Part of the Highway Operational Improvements in Las Virgenes and Malibu Subregion

Region(s): Las Virgenes/Malibu
City: Westlake Village
$1.5M Ongoing

East San Fernando Valley Transit Corridor Project

Transit improvements on four potential East San Fernando Valley corridors, including Van Nuys, Sepulveda, Reseda and Lankershim between Ventura Bl. and south of the 118 freeway.

Region(s): San Fernando Valley
City: Los Angeles
More: Project Website
$TDB Alternative Analysis Study

I-5/SR-134 TSM Project SR-2 to Hollywood Way Incl. Ramp Meters, CCTV, CMS

TBD

Part of the Highway Operational Improvements in Arroyo Verdugo Subregion

Region(s): Arroyo Verdugo
City: Glendale
$TBD Ongoing

Kanan Bridge Widening

TBD

Part of the Highway Operational Improvements in Las Virgenes and Malibu Subregion

Region(s): Las Virgenes/Malibu
City: Agoura Hills
$TBD Ongoing

Kanan Road Overpass Expansion - PSR, PR, PS&E

TBD

Part of the Highway Operational Improvements in Las Virgenes and Malibu Subregion

Region(s): Las Virgenes/Malibu
City: Agoura Hills
$5M Ongoing

Liberty Canyon Overpass

TBD

Part of the Highway Operational Improvements in Las Virgenes and Malibu Subregion

Region(s): Las Virgenes/Malibu
City: Calabasas
$TBD Ongoing

Malibu Canyon Road Widening

TBD

Part of the Highway Operational Improvements in Las Virgenes and Malibu Subregion

Region(s): Las Virgenes/Malibu
City: Calabasas
$3M Ongoing

Malibu/Civic Center Way Widening

TBD

Part of the Highway Operational Improvements in Las Virgenes and Malibu Subregion

Region(s): Las Virgenes/Malibu
City: Malibu
$4M Ongoing

Malibu/Pacific Coast Highway Bike Lane

TBD

Part of the Highway Operational Improvements in Las Virgenes and Malibu Subregion

Region(s): Las Virgenes/Malibu
City: Malibu
$6M Ongoing

Mureau Road Overpass

TBD

Part of the Highway Operational Improvements in Las Virgenes and Malibu Subregion

Region(s): Las Virgenes/Malibu
City: Calabasas
$0.5M Ongoing

Off-Ramp for US 101 at Las Virgenes Road

TBD

Part of the Highway Operational Improvements in Las Virgenes and Malibu Subregion

Region(s): Las Virgenes/Malibu
City: Calabasas
$0.5M Ongoing

SR-134/Brand Bl Westbound Offramp Widening

TBD

Part of the Highway Operational Improvements in Arroyo Verdugo Subregion

Region(s): Arroyo Verdugo
City: Glendale
$TBD Ongoing

Crenshaw/LAX Transit Corridor (project acceleration)*

Accelerates construction of a line along the Crenshaw Bl Corridor and connects Los Angeles, Inglewood, Hawthorne and El Segundo, plus unincorporated LA County.

Region(s): City of Los Angeles, South Bay cities
More: Project Website
$1.21B Preliminary Engineering

East Light Rail Access (Gold Line)

Increases access, including pedestrian and bicycle, to the Gold Line Eastside Light Rail project.

Region(s): City of Los Angeles
More: Project Website
$30.0M Ongoing

Eastside Transit Corridor Phase 2

Extends Metro Gold Line farther east from the Pomona/Atlantic Station.

Region(s): Gateway Cities, San Gabriel Valley
More: Project Website
$1.27B MIS/EIR/EIS/EA Draft Phase

Exposition Transit Corridor, Phase II

Extends the Exposition Rail Line, currently under construction to Culver City, to Santa Monica.

Region(s): City of Los Angeles, Westside cities
City: Los Angeles
More: Project Website
$925M Construction

Gold Line Foothill Extension

Extends the Metro Gold Line from its current terminus in Pasadena toward Claremont.

Region(s): San Gabriel Valley
More: Project Website
$735M Construction

Green Line Extension to Los Angeles International Airport*

Links the Metro Green Line to LAX at the Aviation Station.

Region(s): City of Los Angeles, South Bay cities
More: Project Website
$200M Alternative Analysis Study

Metro Orange Line Extension

Extends the Metro Orange Line north from Canoga Park Station to Chatsworth with a projected completion three years early.

Region(s): City of Los Angeles, San Fernando Valley
More: Project Website
$182M Construction

Metro Rail Capital Projects

Maintains rail facilities by improving operational systems, upgrading rail yards and purchasing new rail cars.

Region(s): Regionwide Programs
$788M Ongoing

Metrolink Capital Improvement Projects (Los Angeles County)

Purchases trains, expands the Eastern Maintenance Facility and upgrades sidings and crossovers to increase speed and safety. Local jurisdictions could use funds to improve parking and station facilities within their cities and offer connecting shuttle services.

Region(s): Regionwide Programs, San Fernando Valley
$1.18B Ongoing

Regional Connector: Transit Corridor*

Links four light rail lines that terminate at the edges of Central LA. Expected to provide seamless connections between Long Beach/Claremont, and Culver City/East LA, minimizing the need for rail transfers.

Region(s): City of Los Angeles, Gateway Cities, San Gabriel Valley, South Bay cities, Westside cities
More: Project Website
$160M Preliminary Engineering Advanced Conceptual Engineering/Preliminary Engineering

Sepulveda Pass Transit Corridor

Provides a rapid transit option to improve traffic flow between the Westside and the San Fernando Valley through the Sepulveda Pass along the I-405 freeway corridor. It will provide a viable alternative to driving on a heavily congested freeway. Specific transit technology and routing will be subject to approved plans developed in cooperation with local jurisdictions and affected communities.

Region(s): City of Los Angeles, San Fernando Valley
More: Project Website
$1.0B Initial Planning

South Bay Green Line Extension*

Extends the Metro Green Line from its current terminus in Redondo Beach to the South Bay Galleria.

Region(s): South Bay cities
More: Project Website
$272M MIS/EIR/EIS/EA Draft Phase

West Santa Ana Transit Corridor

Provides for the development of a grade-separated transit corridor. Phase I is designed to go from the LA County line toward downtown LA.

Region(s): City of Los Angeles, Gateway Cities
More: Project Website
$240M Alternative Analysis Study

Westside Subway Extension (to be opened in segments)

Extends Metro Rail to the Westside. The project is expected to serve Century City and Westwood/UCLA.

Region(s): City of Los Angeles, Westside cities
More: Project Website
$4.07B MIS/EIR/EIS/EA Final Phase & Preliminary Engineering

Bicycle Programs**

Development of bicycle facilities throughout Los Angeles County.

Region(s): Regionwide Programs
$ Awarded to cities by population Ongoing

Highway 101 Park and Ride

Design and construct a Park and Ride facility at the proposed community recreational facility.

Part of the Highway Operational Improvements in Las Virgenes and Malibu Subregion

Region(s): Las Virgenes/Malibu
City: Westlake Village
$2.1M Completed

Major Street Resurfacing & Pothole Repair**

Accelerated repair of potholes and other street and curb damage.

Region(s): Regionwide Programs
$ Awarded to cities by population Ongoing

Pedestrian Improvement Program**

Improvements for pedestrians such as retrofitting existing facilities with enhanced signage and safety components.

Region(s): Regionwide Programs
$ Awarded to cities by population Ongoing

Safer Bus Stops**

Enhancements to bus stops such as lighting, electronic real-time arrival signage, shelters and electronic surveillance.

Region(s): Regionwide Programs
$ Awarded to cities by population Ongoing

Signal Synchronization**

Coordinated operation of traffic signals, including left-turn arrows at intersections, to improve traffic flow.

Region(s): Regionwide Programs
$ Awarded to cities by population Ongoing

Traffic Demand Management**

Strategies to offer alternatives to drive-alone vehicle travel. They include improving the efficiency of existing transportation infrastructure, eliminating vehicle trips and deployment of new technologies.

Region(s): Regionwide Programs
$ Awarded to cities by population Ongoing

Traffic Monitoring Programs**

Expand regional traffic monitoring systems, which provide continuous, real-time traffic and incident data to control centers and the public.

Region(s): Regionwide Programs
$ Awarded to cities by population Ongoing

Agoura Road Widening

Widen Agoura Road and Canwood St.

Part of the Highway Operational Improvements in Las Virgenes and Malibu Subregion

Region(s): Las Virgenes/Malibu
City: Agoura Hills
$5.5M Final Design

Citywide Signal Sync/Traffic Operations Center

Construct and implement Citywide Signal Synchronization and Traffic Operations Center.

Part of the Highway Operational Improvements in Las Virgenes and Malibu Subregion

Region(s): Las Virgenes/Malibu
City: Agoura Hills
$2M Final Design

Fairmont Av Grade Separation at San Fernando Road

Provides grade separation of Fairmont Av over San Fernando Road and includes construction of a Park-and-Ride facility.

Part of the Highway Operational Improvements in Arroyo Verdugo Subregion

Region(s): Arroyo Verdugo
City: Glendale
$3M Construction

High Desert Corridor Project (environmental)***

Provides the initial study of the High Desert Corridor, linking the Antelope Valley to Apple Valley.

Region(s): North Los Angeles County
$33.0M MIS/EIR/EIS/EA Draft Phase

I-405, I-110, I-105, SR-91 Ramp/Interchange Improvements: South Bay

Constructs improvements in the South Bay to reduce delays on the freeways. Examples include auxiliary lanes and ramp reconfigurations.

Region(s): City of Los Angeles
$906M Construction

I-5 Corridor Arterial Signal Improvements

Provide traffic signal upgrades, signal controller upgrades, and variable timing plans to intersections on arterial streets within 1 mile of the I-5 corridor.

Part of the Highway Operational Improvements in Arroyo Verdugo Subregion

Region(s): Arroyo Verdugo
City: Burbank
$TBD Ongoing

I-5 HOV from SR-134 to SR-170

Constructs one carpool lane in each direction along the I-5 freeway between SR-134/SR-170, including access improvement for Empire Av.

Region(s): Arroyo Verdugo, City of Los Angeles
$272M Construction

I-5 North Capacity Enhancements: SR-14 to Kern County Line (Truck Lanes)***

Adds a carpool lane and a dedicated truck lane in both directions on the I-5 freeway north of SR-14 in the Santa Clarita Valley.

Region(s): North Los Angeles County
$410M Ongoing Seg. 1 - Construction, Seg. 2 - Design, Seg. 3 - Initial Planning

I-5 Widening and HOV: I-605 to Orange County Line

Constructs one carpool lane and one mixed-low lane in each direction extending 6.4 miles through Cerritos, La Mirada, Santa Fe Springs and Norwalk. Includes interchange reconstruction and arterial modifications.

Region(s): Gateway Cities
$265M Final Design

I-5/Carmenita Road Interchange

Removes existing two-lane structure and constructs a new eight-lane interchange with carpool lane on-ramps. Project is located in Santa Fe Springs and Norwalk, and could enable widening of I-5 in the area.

Region(s): Gateway Cities
$138M Construction

I-5/Olive Av - Verdugo Av Northbound Ramps Auxiliary Lane

Reconfigure the existing Northbound Olive Av ramp system with I-5 to provide a continuous auxiliary lane between Alameda Av and Burbank Bl, by reconfiguring Bonnywood Place and the existing ramps at Angeleno and Orange Grove.

Part of the Highway Operational Improvements in Arroyo Verdugo Subregion

Region(s): Arroyo Verdugo
City: Burbank
$TBD Ongoing

I-5/SR-14 HOV Direct Connector

Provides direct link for carpoolers between I-5 and SR-14 freeways, which eliminates need to exit carpool lanes when switching freeways.

Region(s): North Los Angeles County
$90.8M Construction

I-605 Corridor "Hot Spot" Interchanges

Improvements to interchanges along the I-605 corridor, such as at the SR-60, I-5, SR-91 and I-405 interchanges. Examples of improvements include roadway widening, ramp expansion and added signage within the interchange.

Region(s): Gateway Cities
$590M Alternative Analysis Study

I-710 Corridor Project EIS/EIR***

Upgrades the freeway and improves truck and traffic flows between the Ports of Los Angeles and Long Beach and the SR-60 freeway. Also to be considered are upgrades to the I-710 freeway between Pacific Coast Highway and downtown Long Beach.

Region(s): Gateway Cities
$590M MIS/EIR/EIS/EA Draft Phase

Las Virgenes Scenic Corridor Widening

Widen the Las Virgenes Road Scenic Corridor in order to improve traffic flow and safety.

Part of the Highway Operational Improvements in Las Virgenes and Malibu Subregion

Region(s): Las Virgenes/Malibu
City: Calabasas
$4M Completed

Lost Hills Overpass and Interchange

Construct a new interchange and overcrossing to replace the current Lost Hills Road/US 101 interchange.

Part of the Highway Operational Improvements in Las Virgenes and Malibu Subregion

Region(s): Las Virgenes/Malibu
City: Calabasas
$9.5M Final Design

Monterey Road Extension to Glenoaks Bl over Verdugo Wash

Construction of a bridge to connect Monterey Road to Glenoaks Bl. This project would create a continuous frontage road to connect the existing SR-134/Central/Brand Bl split-diamond interchange to the SR-134/Glendale Av interchange.

Part of the Highway Operational Improvements in Arroyo Verdugo Subregion

Region(s): Arroyo Verdugo
City: Glendale
$TBD Ongoing

Mulholland Highway Hillside Removal

Widen intersections, approaches to intersections and provide dedicated left turn and bypass lanes along Mulholland Highway.

Part of the Highway Operational Improvements in Las Virgenes and Malibu Subregion

Region(s): Las Virgenes/Malibu
City: Calabasas
$2M Ongoing

Mulholland Highway Scenic Corridor Completion

Widen intersection, approaches to intersections and provide dedicated left turn and bypass lanes along Mulholland Highway.

Part of the Highway Operational Improvements in Las Virgenes and Malibu Subregion

Region(s): Las Virgenes/Malibu
City: Calabasas
$7.25M Final Design

Palo Comado Interchange

Complete interchange improvements along Palo Comado Canyon Road, the intersection of Driver Av and Chesebro Road.

Part of the Highway Operational Improvements in Las Virgenes and Malibu Subregion

Region(s): Las Virgenes/Malibu
City: Agoura Hills
$22.85M Initial Planning

Parkway Calabasas/US 101 Soutbound Offramp

Re-design the Parkway Calabasas/US 101 southbound interchange for greater traffic flow and safety.

Part of the Highway Operational Improvements in Las Virgenes and Malibu Subregion

Region(s): Las Virgenes/Malibu
City: Calabasas
$0.35M Completed

Roundabout

Construct a 2-lane road roundabout at the intersection of Kanan Road and Agoura Road.

Part of the Highway Operational Improvements in Las Virgenes and Malibu Subregion

Region(s): Las Virgenes/Malibu
City: Agoura Hills
$5.25M Final Design

San Fernando Bl/Burbank Bl Intersection Improvement

Widen San Fernando/Burbank intersection to improve intersection operations.

Part of the Highway Operational Improvements in Arroyo Verdugo Subregion

Region(s): Arroyo Verdugo
City: Burbank
$8M Initial Planning

San Fernando/Grandview At-Grade Rail Crossing Improvements

Safety improvements to the existing at-grade rail crossing at San Fernando Road and Grandview Av. The improvements include the installation of a state-of-the-art advance pre-emption system, installation of quad gates, and adjustment of the roadway approach grade at the railroad track.

Part of the Highway Operational Improvements in Arroyo Verdugo Subregion

Region(s): Arroyo Verdugo
City: Glendale
$2.2M Construction

Sonora Av At-Grade Rail Crossing Safety Upgrade

Safety improvements to the existing at-grade rail crossing at Sonora Av. The improvements include the installation of a state-of-the-art advance pre-emption system, installation of quad gates, and adjustment of the roadway approach grade at the railroad track.

Part of the Highway Operational Improvements in Arroyo Verdugo Subregion

Region(s): Arroyo Verdugo
City: Glendale
$2,700 Construction

SR-134 Corridor Arterial Signal Improvements

Provide traffic signal upgrades, signal controller upgrades, and variable timing plans to intersections on arterial streets within 1 mile of the SR-134 corridor.

Part of the Highway Operational Improvements in Arroyo Verdugo Subregion

Region(s): Arroyo Verdugo
City: Burbank
$TBD Ongoing

SR-134 Ramps/Harvey Dr/Wilson Av Signal & Street Widening

Upgrading the traffic signal at the SR-134 Eastbound and Westbound on and off ramps with Harvey Dr, upgrading the traffic signal at this intersection, and widening the Harvey Dr and Wilson Av intersection.

Part of the Highway Operational Improvements in Arroyo Verdugo Subregion

Region(s): Arroyo Verdugo
City: Glendale
$1.1M Ongoing

SR-134/Central Av Eastbound Offramp Widening

Add an additional lane to the SR-134 Eastbound off-ramp at Central Av to alleviate traffic back up on Central Av off-ramp, SR-134 eastbound auxiliary lane, and freeway main line.

Part of the Highway Operational Improvements in Arroyo Verdugo Subregion

Region(s): Arroyo Verdugo
City: Glendale
$3.5M Ongoing

SR-134/Glendale Av Interchange Modification

Upgrading the traffic signal at the SR-134 Eastbound on and off ramps and Glendale Av, upgrading the traffic signal at Glendale Av and Monterey Road and adding a left turn lane, and installation of interconnect cable for the westbound on-ramp and westbound off-ramp.

Part of the Highway Operational Improvements in Arroyo Verdugo Subregion

Region(s): Arroyo Verdugo
City: Glendale
$3M Ongoing

SR-134/Pacific Av Eastbound Offramp Widening

Add an additional lane to the SR-134 Eastbound off-ramp at Pacific Av to alleviate traffic back up on the Pacific Av off-ramp and freeway main line.

Part of the Highway Operational Improvements in Arroyo Verdugo Subregion

Region(s): Arroyo Verdugo
City: Glendale
$0.3M Ongoing

SR-134/Pacific Av Westbound Offramp Widening

Add an additional lane to the SR-134 Westbound off-ramp at Pacific Av to alleviate traffic back up on the Pacific Av off-ramp and freeway main line.

Part of the Highway Operational Improvements in Arroyo Verdugo Subregion

Region(s): Arroyo Verdugo
City: Glendale
$0.3M Ongoing

SR-138 Capacity Enhancements

Widens SR-138 by adding new lanes in each direction to the San Bernardino County line.

Region(s): North Los Angeles County
$200M Alternative Analysis Study

SR-2/Holly Dr Interchange Ramp Signalization

Installation of a traffic signal at the intersection of Holly Dr and the SR-2 Freeway on and off ramps.

Part of the Highway Operational Improvements in Arroyo Verdugo Subregion

Region(s): Arroyo Verdugo
City: Glendale
$.5M Ongoing

SR-2/Mountain Av Interchange Ramp Widening

Widening the Northbound and Southbound off-ramps at the Mountain Av interchange with SR-2.

Part of the Highway Operational Improvements in Arroyo Verdugo Subregion

Region(s): Arroyo Verdugo
City: Glendale
$.6M Ongoing

SR-2/SR-134 Interchange Fwy-to-Fwy Ramp Meters

Installation of Ramp Metering on the SR-2 Southbound to SR-134 Westbound connector ramp. Also includes the installation of Ramp metering on the SR-134 to SR-2 Northbound connector ramp.

Part of the Highway Operational Improvements in Arroyo Verdugo Subregion

Region(s): Arroyo Verdugo
City: Glendale
$3M Ongoing

SR-2/Verdugo Bl Intersection Signalization

Installation of a traffic signal at the SR-2 / Verdugo Bl on ramp.

Part of the Highway Operational Improvements in Arroyo Verdugo Subregion

Region(s): Arroyo Verdugo
City: Glendale
$700 Ongoing

SR-710 Project Gap Closure***

Improvements to connection between SR-710 and I-210 freeways.

Region(s): San Gabriel Valley
$780M Initial Planning

US 101/Lindero Canyon Road Interchange Improvements

Widen Lindero Canyon Road to add additional travel lanes and widen and extend US 101/Lindero Canyon Road Interchange's ramp.

Part of the Highway Operational Improvements in Las Virgenes and Malibu Subregion

Region(s): Las Virgenes/Malibu
City: Westlake Village
$9.5M Construction

Widen Magnolia Bl/I-5 Bridge for center-turn lane, standard lanes, shoulders

Widen Magnolia Bridge over I-5 to provide standard-width travel lanes, a continuous two-way left turn lane to serve both sides of the bridge, five-foot shoulders, and widened sidewalks.

Part of the Highway Operational Improvements in Arroyo Verdugo Subregion

Region(s): Arroyo Verdugo
City: Burbank
$2.3M Ongoing

Widen Olive Av/I-5 Bridge for center-turn lane, standard width lanes, shoulders

Widen Olive Av Bridge over I-5 to provide standard-width travel lanes, a continuous two-way left turn lane to serve both sides of the bridge, five-foot shoulders, and widened sidewalks. 

Part of the Highway Operational Improvements in Arroyo Verdugo Subregion

Region(s): Arroyo Verdugo
City: Burbank
$TBD Ongoing

Expanded Community-based Shuttle Services**

Continuation and expansion of community-based circulators.

Region(s): Regionwide Programs
$ Assigned from 20% of total funds Ongoing

Express Bus Improvements**

Continued operation and expansion of express bus service. Express lines use existing rights-of-way to provide efficient long-distance service.

Region(s): Regionwide Programs
$ Assigned from 20% of total funds Ongoing

Fares

The per-passenger cost of providing transit service is much higher than the fares charged to riders. As a result, transit service is subsidized. Measure R is expected to allow Metro to maintain its fares for one year and freeze fares for seniors, students, the disabled and commuters for five years.

Region(s): Regionwide Benefits
$ Assigned from 20% of total funds Ongoing

Improved Service for Seniors**

Continuation and expansion of efforts such as dedicated hands-on "sampler" buses, large-type mapping and route planning tools, outreach to senior centers and retirement homes, specialized large-type informational materials and audience-appropriate training videos.

Region(s): Regionwide Programs
$ Assigned from 20% of total funds Ongoing

Improved Service for the Disabled**

Continuation and expansion of enhancements on buses such as wheelchair lifts or ramps, automated voice enunciators and electronic signage to call out stops for visually and hearing impaired passengers.

Region(s): Regionwide Programs
$ Assigned from 20% of total funds Ongoing

Increased Bus Service to Rail Stations**

Continuation and expansion of connecting bus lines at various stations to increase access to rail lines.

Region(s): Regionwide Programs
$ Assigned from 20% of total funds Ongoing

Increased Local Transit Funding**

Continuation and expansion of municipal transit operator funding and other locally-based transit service providers.

Region(s): Regionwide Programs
$ Assigned from 20% of total funds Ongoing

Local Bus Improvements**

Improvements in the quality and reliability of local bus service over the next 30 years, such as utilization of higher capacity buses. Region(s): Regionwide Programs
$ Assigned from 20% of total funds Ongoing

Rapid Bus Improvements**

Continued operation of the Metro Rapid network with over 400 miles of service throughout Los Angeles County. These lines make fewer stops, follow simpler routes, run more frequently, use low-door buses to facilitate boarding and are given priority at certain traffic signals.

Region(s): Regionwide Programs
$ Assigned from 20% of total funds Ongoing

Alameda Corridor East Grade Separations Phase II

Constructs bridges or underpasses and improves the operation of other railroad intersections along a 35-mile stretch of the San Gabriel Valley.

Region(s): San Gabriel Valley
$400M Final Design

Alternative to High Gas Prices

Measure R funds are expected to offer alternatives to drive-alone vehicles.

Region(s): Regionwide Benefits
Ongoing

Burlington Northern Santa Fe Grade Separations

Construction of rail and roadway grade separations in the Gateway Cities area at five locations including: Rosecrans Av and Marquardt Av, Passons Bl, Los Nietos Road and Norwalk Bl, Lakeland Road and Pioneer Bl.

Region(s): Gateway Cities
$35.0M Ongoing

Countywide Soundwall Construction

Continued construction of soundwall projects for major highway projects to reduce freeway noise levels.

Region(s): Regionwide Programs
$250M Ongoing

Job Stimulus

According to the Los Angeles County Economic Development Corporation, Measure R would create over 210,000 new jobs and add more than $32 billion into Los Angeles County's economy.

Region(s): Regionwide Benefits
Ongoing

Metro and Municipal Regional Clean-fuel Bus Capital Facilities and Rolling Stock

Purchase of clean-fuel buses by both Metro and municipal operators.

Region(s): Regionwide Programs
$150M Ongoing

Soundwalls on I-210

Design and construct certain soundwall segments along the I-210 freeway within the City of La Cañada Flintridge.

Part of the Highway Operational Improvements in Arroyo Verdugo Subregion

Region(s): Arroyo Verdugo
City: La CaƱada Flintridge
$4.588M Initial Planning



Here's how it works: The Measure R Projects Tracker lists the various projects in alphabetical order by category with a brief description of the project.1 You can view the status for many of the projects with estimated Measure R funding allocations as projected over 30 years.2


  • *Specific mode and routing will be subject to approved plans developed in cooperation with local jurisdictions and affected communities.
  • **Specific improvements are expected to be developed by local jurisdictions.
  • ***Partial funding by public/private partnerships is assumed to be part of the project plan.

1Projects listed are for reference only and do not indicate priority order. Project definition depends on final environmental process.
2Measure R does not fully fund all projects.