Notice of Night Work Activity - July 30

ATTENTION RESIDENTS IN THE VICINITY OF SEPULVEDA BL AT MORAGA DR

Construction of the freeway drainage system at the Sepulveda Bl andMoraga Dr intersection is anticipated to start on Monday, July 30, 2012.

What: Freeway drainage system 

When: Work is anticipated to start on Monday, July 30, 2012 through August 30, 2012.  Anticipated work hours are from 9pm to 6am.

Where: NB Sepulveda Bl at Moraga Dr intersection

What to expect:

  • Sepulveda Bl will be reduced to one lane in each direction during work hours.
  • The Moraga ramps may be closed intermittently at 7pm; traffic will be detoured to the Getty ramps. 
  • This operation involves the saw cutting, street grinding, setting of metal plates, potholing to identify underground utilities, excavation and installation of storm drain line.
  • Access to pedestrians will be maintained outside the work zone.
  • Emergency access will be maintained.