Home > Projects & Programs > Construction Notices > I-405 Sepulveda Pass ... > Notice of Day Work Activity ...
Sewer line installation work will commence along Sepulveda Bl between Montana Av and the Sunset Bl bridge for approximately five months, requiring daily closures of the intersection of Homedale at Sepulveda and Bronwood at Sepulveda.
What: Sewer line relocation
When: Activities are anticipated to start on Monday, November 7, 2011 for approximately five months. Anticipated work hours are from 4am to 8pm, weather permitting.
Where: Sepulveda Bl between Montana Av Sunset Bl bridge
What to expect:
Please note that construction is a dynamic process and subject to change without notice.
Thank you for your patience and cooperation
For more information, call the Community Relations Construction Impact Team at 213.922.3665.
Metro Community Relations
6060 Center Dr, 2nd Fl
Los Angeles, CA 90045