Home > Projects & Programs > Construction Notices > I-405 Sepulveda Pass ... > Construction Notice - September 19, ...

Construction Notice - September 19, 2012

ATTENTION RESIDENTS IN THE VICINITY OF SEPULVEDA BL BETWEEN HOMEDALE AV AND BRONWOOD AV

Pile setting operations at the north end of Wall 1730, near Bronwood Av, are anticipated to start on Wednesday, September 19, 2012 during daytime hours, in preparation for backfill operations.

What: Pile drilling

When: Pile drilling work is anticipated to start on Wednesday, September 19, 2012 for approximately three weeks. Nighttime operations may be scheduled at a later time. Anticipated work hours are from 6am to 7pm and 9pm to 6am.

Where: Sepulveda Bl hillside between Bronwood Av alleyway and Bronwood Av

What to expect:

  • Work crews will be working adjacent to private property lines.
  • This operation involves the drilling, setting and pouring of soldier pile, lagging and backfill; nighttime operations may be scheduled at a later time.
  • Sepulveda Bl traffic will be reduced to one lane in each direction during daytime work hours.
  • Sepulveda Bl will be fully closed between Montana Av and Church Ln during nighttime work hours to support continued critical utility relocation. Sepulveda Bl traffic will be detoured to Church Ln.

For viewing MS Word, Powerpoint, and Excel documents - Download Adobe Acrobat Reader (free) or use Google Docs Reader (online)