Construction Notice - July 9

ATTENTION RESIDENTS AND BUSINESS OWNERS IN THE VICINITY OF SEPULVEDA BL BETWEEN MORAGA DR AND GETTY CENTER DR

Construction of the wall on the west side of Sepulveda Bl between Moraga Dr and Getty Center Dr will start on Monday, July 9, 2012.

What:        

Wall construction

When:       

Work is anticipated to start on Monday, July 09, 2012 for approximately 13 weeks.  Daytime work hours are from 7am to 4pm.  Nighttime activities are from Monday through Saturday 9pm to 6am.

Where:      

West side of Sepulveda Bl between Moraga Dr and Getty Center Dr

What to expect:

  • Access to residents and businesses will be maintained.
  • Sepulveda Bl traffic will be maintained with one lane in each direction between the hours of 9am to 4pm and 9pm to 6am.
  • Daytime activities include setting of panels, truck deliveries and some concrete pours.
  • Nighttime activities include backfill and compaction operations.
  • Emergency vehicle access will be maintained.