Home > Projects & Programs > Construction Notices > I-405 Sepulveda Pass ... > Construction Notice: February 27 - ...

Construction Notice: February 27 - Segment 1, Wilshire (National to Waterford)

Construction snapshot what will

Drainage Installation

The contractor will continue working on installing a drainage line along and under the EB 10 to SB 405 connector ramp, starting Monday, February 27, 2012 for approximately three months.

Work will occur during the day from 7:00 am to 5:00 pm and also at night from 9:00 pm to 5:00 am. There will be intermittent closure of the EB 10 connector ramp to SB 405 from 9:00 pm to 5:00 am.

Work will include excavation and installing pipes.

Effects on the freeway

There will be intermittent closures of the EB 10 connector ramp to SB 405 from 9:00 pm to 5:00 am.

Effects on city streets

There will be no effects on city streets.

What will this work accomplish?

When work is complete, a new drainage line will be installed.

A word on impacts

Connector closures will only occur when necessary. Noise will be monitored.

Emergency access

Emergency access will be maintained.


For viewing MS Word, Powerpoint, and Excel documents - Download Adobe Acrobat Reader (free) or use Google Docs Reader (online)