ATTENTION RESIDENTS AND COMMUTERS IN THE VICINITY OF THE SOUTHBOUND I-405 GETTY ON-RAMP AT SEPULVEDA BL

A weekend closure of the SB Getty on-ramp has been scheduled to start at 7pm Friday, August 24, 2012 through 6am Monday, August 27, 2012, to reconfigure the ramp.

What: Weekend ramp closure for reconfiguration

When: Starting at 7pm Friday, August 24, 2012 through 6am Monday, August 27, 2012 the ramp will remain closed 24 hours a day throughout the weekend. 

Where: SB I-405 Getty on-ramp

What to expect:

  • SB Sepulveda Bl lanes will be closed from approximately 200 feet north of the SB Getty on-ramp to the Sepulveda Bl Bridge.  Traffic will be maintained with one lane in each direction between the hour of 9pm Friday night and 3pm on Saturday.
  • SB I-405 lanes #3 and #4 will be closed starting at 10pm through 6am between the Sepulveda Bl Bridge and the Getty Center Drive Bridge.
  • During this activity there will be roadway demo, earthworks, paving, striping, and k-rail reconfiguration. 
  • At its completion, the SB Sepulveda Bl right turn pocket into the ramp will be restored.
  • Pedestrians will be rerouted outside the construction zone.