Closures


Typical Freeway Closure Schedule

Get construction updates on Twitter

Scheduled Extended Closures

Activity Date Duration Closure Type
Bridge 10 and 11 (Wilshire Bl WB – NB on-ramp and NB – WB off-ramp) Mid-March  90 Days Full ramp closure
Bridge 9 – set false work December 5 to January 30 Nightly Wilshire Bl – Full street closure
Erecting bridge 5B pre-cast girders Early March Nightly Ohio Av – Full street closure
Erecting bridge 6A steel girders June Nightly Wilshire Bl – Full street closure
Skirball sewer and water January Nightly Full street closure / Full SB on- and off-ramp closure

 

City Streets

Activity Closure Type Closure Opening
Day work Lane 9 am 3 pm
Night work Lane 9 pm 6 am

Southbound I-405

Activity Closure Type Closure Opening
Mainline Complete Midnight 6 am
Mainline Lane 7 pm 6 am
Mainline On-ramps 7 pm 6 am
Mainline Off-ramps 7 pm 6 am
Freeway connector Southbound I-405 to US 10 9 pm 6 am
Freeway connector US 10 to southbound I-405 10 pm 6 am
Freeway connector Southbound I-405 to US 101 7 pm 6 am
Freeway connector US 101 to southbound I-405 10 pm 6 am

Northbound I-405

Activity Closure Type Closure Opening
Mainline Complete Midnight 6 am
Mainline Lane 7 pm 6 am
Mainline On-ramps 7 pm 6 am
Mainline Off-ramps 7 pm 6 am
Freeway connector Northbound I-405 to US 10 10 pm 6 am
Freeway connector US 10 to northbound I-405 9 pm 6 am
Freeway connector Northbound I-405 to US 101 9 pm 6 am
Freeway connector US 101 to northbound I-405 10 pm 6 am

 

 

Although there may be some variance in these times, the majority of closures occur during these times. The contractor may close a freeway ramp during day hours, although this would be a rare occurrence.

Stay Connected
Receive email alerts and follow on the web.
  • Get e-mail updates
  • Get updates at facebook.com/405project
  • Get updates at twitter.com/I_405
  • Get updates at local.nixle.com/i-405-sepulveda-pass-improvements-project
  • Get traffic updates at go511.com




Did You Know?

Community Relations Team:
Kasey Shuda -Wilshire Segment (National Bl to Waterford St)
Tel: 310.846.3563
Olga N. Arroyo - Sunset Segment (Waterford St to Sepulveda Bl)
Tel: 310.846.2357
Ron Macias - Mulholland Segment (Sepulveda Bl to Ventura Bl)
Tel: 310.846.3564
Ned Racine - New Media
Tel: 310.846.3569
Yvette ZR Rapose - Director of Construction Relations
Tel: 213.922.2297

Contact Information:
Metro Community Relations 
6060 Center Dr, 2nd Fl
Los Angeles, CA 90045-2952

Tel: 213.922.3665
I405@metro.net
Sign up for our email list



Click on the segment name for more information.
Sunset Bridge Demolition & Reconstruction
Status: Ongoing
Click on the segment name for more information.
Skirball Center Dr Bridge Demolition & Reconstruction
Status: Completion of the north side of Skirball Bridge is expected in 2011.

Click on the segment name for more information.
Mulholland Dr Bridge Demolition & Reconstruction
Status: Completion of the south side of Mulholland Bridge is anticipated for summer 2012.
Click on the segment name for more information.
Wilshire Bl Ramps Reconstruction
Status: Construction of the Wilshire on- and off-ramps is anticipated to begin in the First Quarter 2012.