Moving the spaghetti of utilities under Sepulveda Bl


Bonnie Verdin loves spaghetti, although she wishes she saw less of it during her work day.

Verdin is not a chef. For the I-405 Improvements Project, her title is Supervisor, Third Party Administration, but when she thinks of the tangle of underground utilities that must be moved to construct the project, she sees spaghetti.

"There's a huge amount of utilities under this project," she explains. "They resemble spaghetti under Sepulveda Bl. And we're shifting Sepulveda east in some locations. And when you shift, you have to shift the utilities, sewers, water lines, etc."

As an example, she describes the area near the Getty Center as having "multiple utilities and limited space." Engineers refer to underground utilities as subsurface infrastructure. Under any term, Verdin has discovered it's a challenge for project designers to create a utility corridor that holds everything.

Verdin has coordinated the relocation of utilities for large transportation projects since her work on the Metro Orange Line and Gold Line Eastside Extension. She has been working in third party administration ("third party" being other government organizations and the owners of utilities) since 1993. She has worked on the I-405 project since its inception.

Because of the menu of utilities within the project boundaries-she estimates that there are 24 utility owners affected-this will be her greatest challenge. Add to that the government jurisdictions with a stake in those utilities, and Verdin sees more spaghetti.

"Utility relocation can be a major threat to the schedule," she explained. "So we have to design and relocate the utilities within the contractor's aggressive time line."

What are the utilities snoozing underneath the Sepulveda Pass?

Shell, Chevron, Exxon and Mobil have oil pipelines through the pass. SCS Energy has a natural gas pipeline to UCLA. There are fiber optics lines. Southern California Gas Company and Southern California Edison bring gas and electricity to their customers through the pass.

Verizon and ATT connect residences and business via the Sepulveda Pass, and Metropolitan Water District has a 96-inch-diameter water line under Sepulveda Bl.

Some of those utilities run along and through the three bridges to be replaced-Sunset, Skirball and Mulholland-complicating their demolition and reconstruction.

Verdin, whose training was in food nutrition science, began as the only third party administrator on the I-405 project, but she has since been joined by Alvin Trotter, third-party administrator, and consultants Philip Roupas and Ed Castaneda.

"Our days are typically consumed by meetings, fielding questions and finishing the issues that spring from those meetings," Verdin summarizes. Her major task is to reach agreement on a design and alignment that hold all this spaghetti.

    Kiewitt Grubbing
    The third-party administration team poses before a power pole that will be removed to allow the widening of the Ohio Av overpass. From left are consultants Philip Roupas and Ed Castaneda. Bonnie Verdin, who worked on the Metro Orange Line, serves as Supervisor, Third Party Administration. Alvin Trotter, third-party administrator, stands closest to Ohio Av.

Art Correa, Caltran's design manager on the project, suspects that the Sepulveda Pass holds so many utilities because it offered a direct path from Los Angeles and the South Bay into the San Fernando Valley. "Fresh water comes to the Sepulveda Pass from the north, and oil products come from the South Bay to the north," he says.

Noting that Sepulveda Bl predated the I-405 freeway by many years, Correa expected that the boulevard would hold the utilities needed for an area that experienced significant residential growth.

Working on a Caltrans-owned project means Verdin and her staff must play utility detectives to discover who is responsible for paying to move a utility. This varies from Metro projects, where the transportation authority pays for all utility movement.

During preliminary engineering, Caltrans identified what utilities it thought would be affected by I-405 construction. Following subsequent investigations, that number has more than doubled.

"Especially when you're working on old streets, you're bound to find surprises," Verdin has learned. "It's a bit of a challenge for everyone, including the utility owners themselves." Investigators have discovered utilities as old as the 1950s within the project area.

Verdin sees diplomacy as the biggest piece of her role. "You have a contractor with a job to do, to achieve a schedule, but sometimes we have to advocate for the utilities to ensure that the utilities have the information they need. To proceed, you constantly have to reach resolutions."

Ned Racine

Stay Connected
Receive email alerts and follow on the web.
  • Get e-mail updates
  • Get updates at facebook.com/405project
  • Get updates at twitter.com/I_405
  • Get updates at local.nixle.com/i-405-sepulveda-pass-improvements-project
  • Get traffic updates at go511.com




Did You Know?

Community Relations Team:
Kasey Shuda -Wilshire Segment (National Bl to Waterford St)
Tel: 310.846.3563
Olga N. Arroyo - Sunset Segment (Waterford St to Sepulveda Bl)
Tel: 310.846.2357
Ron Macias - Mulholland Segment (Sepulveda Bl to Ventura Bl)
Tel: 310.846.3564
Ned Racine - New Media
Tel: 310.846.3569
Yvette ZR Rapose - Director of Construction Relations
Tel: 213.922.2297

Contact Information:
Metro Community Relations 
6060 Center Dr, 2nd Fl
Los Angeles, CA 90045-2952

Tel: 213.922.3665
I405@metro.net
Sign up for our email list



Click on the segment name for more information.
Sunset Bridge Demolition & Reconstruction
Status: Ongoing
Click on the segment name for more information.
Skirball Center Dr Bridge Demolition & Reconstruction
Status: Completion of the north side of Skirball Bridge is expected in Spring 2012.

Click on the segment name for more information.
Mulholland Dr Bridge Demolition & Reconstruction
Status: Completion of the south side of Mulholland Bridge is anticipated for summer 2012.
Click on the segment name for more information.
Wilshire Bl Ramps Reconstruction
Status: Construction of the Wilshire on- and off-ramps is anticipated to begin in the Second Quarter 2012.