Home > Projects & Programs > I-405 Sepulveda Pass ... > How Do You Drill Under ...


How Do You Drill Under a River of Traffic?


On a typical Wednesday in February 2009, over 120,000 vehicles flow east and west past Veteran Av on Wilshire Bl. If only one person sits in each car-not impossible in Southern California-the number of people traveling on that stretch of Wilshire would exceed the populations of Inglewood or Santa Clara or Costa Mesa.

Closing Wilshire west of the I-405 to construct a sewer, even if those closures occurred during off-peak hours, might petrify even the calmest Los Angeles driver.

Fortunately, jack and bore came to the rescue. Although jack and bore may sound like an unsuccessful folk-rock duo, they are actually a small-diameter tunneling technique that enables a 24-inch-diameter sewer line to be driven under Wilshire Bl, without damming the river that is Wilshire traffic.

Using a 30-inch-diameter auger, which resembles an enormous blue drill bit, workers drill from the Veterans Administration property north of Wilshire Bl to Veterans Administration property south of Wilshire Bl. The "jack" in jack and bore comes from the technique that jacks or drives metal casing through the soil as the auger bores a tunnel.

Two hundred feet of 24-inch-diameter sewer pipe will be installed from north to south, while the same length of 18-inch-wide sewer pipe will be installed beside the first.

Boring a level path for these sewers is critical because sewer lines rely on gravity to continue flowing. For that reason, a specialized probe travels that route first, ensuring that the auger drills a level tunnel.

Because sewer lines are placed deeper underground than other utilities, the boring had to occur below existing utilities that parallel or bisect Wilshire Bl. Workers stand approximately 20 feet below the surface to drive the auger and tunnel casing through the soil under Wilshire Bl.

Workers stand in two excavated boxes with reinforced walls. Once the sewers are completed, these boxes-then closed at the top-will be accessed through manhole covers.


    A worker guides a 24-foot-long auger as a crane lifts it from a work area north of Wilshire Bl. Another auger at the lower left waits to be removed. Chain rigging is used due to the sharp edges and irregular shape of the auger. These photos were taken January 11, 2011.
    A worker guides a 24-foot-long auger as a crane lifts it from a work area north of Wilshire Bl. Another auger at the lower left waits to be removed. Chain rigging is used due to the sharp edges and irregular shape of the auger. These photos were taken January 11, 2011.

 

    Workers use a diesel engine mounted on a short track to extract another auger from the new tunnel under Wilshire Bl.
    Workers use a diesel engine mounted on a short track to extract another auger from the new tunnel under Wilshire Bl.

 

    The specialized probe that ensures the sewer tunnel will have the correct slope waits to be removed from the excavated work area south of Wilshire Bl.
    The specialized probe that ensures the sewer tunnel will have the correct slope waits to be removed from the excavated work area south of Wilshire Bl.

 

    These patient 24-inch-wide sewer pipes wait to be slide into the tunnel underneath Veterans Administration property north of Wilshire Bl.
    These patient 24-inch-wide sewer pipes wait to be slide into the tunnel underneath Veterans Administration property north of Wilshire Bl.

 

    The matching end of the 24-inch-wide sewer pipes shown above.
    The matching end of the 24-inch-wide sewer pipes shown above.

Ned Racine

Stay Connected
Receive email alerts and follow on the web.
  • Get e-mail updates
  • Get updates at facebook.com/405project
  • Get updates at twitter.com/I_405
  • Get updates at local.nixle.com/i-405-sepulveda-pass-improvements-project
  • Get traffic updates at go511.com




Did You Know?

Community Relations Team:
Kasey Shuda -Wilshire Segment (National Bl to Waterford St)
Tel: 310.846.3563
Olga N. Arroyo - Sunset Segment (Waterford St to Sepulveda Bl)
Tel: 310.846.2357
Ron Macias - Mulholland Segment (Sepulveda Bl to Ventura Bl)
Tel: 310.846.3564
Ned Racine - New Media
Tel: 310.846.3569
Yvette ZR Rapose - Director of Construction Relations
Tel: 213.922.2297

Contact Information:
Metro Community Relations 
6060 Center Dr, 2nd Fl
Los Angeles, CA 90045-2952

Tel: 213.922.3665
I405@metro.net
Sign up for our email list



Click on the segment name for more information.
Sunset Bridge Demolition & Reconstruction
Status: Ongoing
Click on the segment name for more information.
Skirball Center Dr Bridge Demolition & Reconstruction
Status: Completion of the north side of Skirball Bridge is expected in Spring 2012.

Click on the segment name for more information.
Mulholland Dr Bridge Demolition & Reconstruction
Status: Completion of the south side of Mulholland Bridge is anticipated for summer 2012.
Click on the segment name for more information.
Wilshire Bl Ramps Reconstruction
Status: Construction of the Wilshire on- and off-ramps is anticipated to begin in the Second Quarter 2012.

I-405 DD promo
Click for discounts along the I-405 Sepulveda Pass Improvements Project corridor



TRANSIT INFO: 323.GO.METRO (323.466.3876) STAY CONNECTED: