| Home | Projects and Studies | Metro Gold Line Eastside Extension | ||
|
To Residents and Business Owners in the Vicinity of the First
Street Bridge Map | Construction Notice NEW DATES: January 28 - February 28, 2008 Starting at 7pm, the First Street bridge (from Mission Road to Vignes Street) will be closed for approximately one month. The Contractor will be building the guideway for the Metro Gold Line Eastside Extension. What to expect:
Note: This 4-week closure will avoid the need for repeated closures during the next ten months. Additional short-term closures may be required due to the widening of the bridge by the City of Los Angeles. Additional traffic reconfigurations over the bridge will be implemented when Metro Gold Line Eastside Extension begins testing trains in the fall of 2008. Please download a map of the affected area featuring all the detours and affected bus stop relocations. If you have further questions, please call 213.922.2259. Copyright © 2008, LACMTA | Privacy Policy |